Permit: T20CM07402
Permit Details
Status:
Expired
Type:
Commercial Building
Address:
3227 N PALO VERDE AV
Address NEW:
3227 N PALO VERDE AV
Apply Date:
10/27/2020
Applicant:
Kathy Nieto
Description:
PARK N SHADE
Permit Reviews
Permit Number - T20CM07402
Permit Status: Expired
Permit Description: PARK N SHADE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/06/2021 | RESUBMITTAL | 02/08/2021 | COMPLETED |
| 02/16/2021 | RESUBMITTAL | 03/17/2021 | COMPLETED |
| 04/07/2021 | RESUBMITTAL | 04/19/2021 | COMPLETED |
| 09/23/2021 | RESUBMITTAL | 10/19/2021 | COMPLETED |
| 10/27/2020 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 12/14/2020 | COMPLETED |
| 10/27/2020 | RESUBMITTAL | 12/21/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM07402
Permit Status: Expired
Permit Description: PARK N SHADE
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 10/27/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
| 11/25/2020 | SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY. |
| 11/25/2020 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. |
| 11/25/2020 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. |
| 11/25/2020 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
| 12/15/2020 | SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS IS REQUIRED. |
Completed Inspections
Permit Status: Expired
Permit Number: T20CM07402
Permit Description: PARK N SHADE
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/22/2021 | COT - LCBU - Excavation/Rebar/Zoning | Passed | {Activity date: 11/22/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by RSALDAT1 - Ap 4 I-beam column footings ok to pour to 11 ft.} |
|
| 12/09/2021 | COT - LCBU - Framing | Passed | {Activity date: 12/09/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by RSALDAT1 - Ap} | |
| 03/24/2022 | COT - LCBU - Building Final | Passed | {Activity date: 03/24/2022; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by VVERA1 - APPROVED BY INSPECTOR AWAITING CONDITIONS} ; {Activity date: 03/24/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Pa Please Ap 1090 and close the permit, when Eng is Ap. } ; {Activity date: 12/09/2021; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by RSALDAT1 - pa Need engineering sign off to be able to approve 1090 and close the permit.} |
|
| 03/24/2022 | ENGR Engineering Final | Passed | {Activity date: 03/24/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by VVERA1 - IS APPROVED } |