Permit: T20CM07296
Permit Details
Apply Date:
10/23/2020
Applicant:
WG GASSER DESIGN LLC
Description:
SFR
Permit Reviews
Permit Number - T20CM07296
Permit Status: Final
Permit Description: SFR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/08/2021 | RESUBMITTAL | 01/20/2021 | ACTIVE |
| 10/23/2020 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 11/13/2020 | COMPLETED |
| 11/13/2020 | RESUBMITTAL | 12/14/2020 | COMPLETED |
| 11/13/2020 | RESUBMITTAL | 12/23/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM07296
Permit Status: Final
Permit Description: SFR
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/23/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T20CM07296
Permit Description: SFR
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/05/2021 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | APPROVED |
| 02/05/2021 | ELECTRIC - UFER | DQUINN | Approved | APPROVED |
| 02/05/2021 | BUILDING PRE-SLAB | DQUINN | Approved | APPROVED |
| 02/05/2021 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | APPROVED |
| 04/02/2021 | ELECTRIC - UNDERGROUND | DQUINN | Approved | Ap Conduit from trans to house, approximately 200’ , and conduit from house to future adjacent house ok to backfill. |
| 04/13/2021 | SITE - SEWER | DQUINN | Approved | APPROVED ABS TO SEPTIC OK TO BACKFILL |
| 04/13/2021 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | APPROVED 2 INCH PVC OK TO BACKFILL |
| 04/13/2021 | ROOF NAILING | DQUINN | Approved | |
| 04/13/2021 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | |
| 05/18/2021 | TEP CLEARANCE - PM | ESTEVENS | Approved | CODE ECO |
| 05/18/2021 | ELECTRIC - CONSTRUCTION POWER | ESTEVENS | Approved | |
| 07/02/2021 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
| 07/02/2021 | RESIDENTIAL INTERMEDIATE | DQUINN | Approved | |
| 10/28/2021 | PLUMBING - FINAL | DQUINN | Approved | Ap |
| 10/28/2021 | MECHANICAL - FINAL | DQUINN | Approved | Ap |
| 10/28/2021 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | Ap |
| 10/28/2021 | ELECTRIC - FINAL | DQUINN | Approved | Ap |
| 10/28/2021 | BUILDING - FINAL | DQUINN | Approved | Ap |
| 10/28/2021 | FRAMING | DQUINN | Approved | Ap |