Permit: T20CM07116
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
3732 E MERCEDES CT
Address NEW:
3732 E MERCEDES CT
Apply Date:
10/15/2020
Applicant:
Clayton Abernathy
Description:
MFR MTVB290718 T18-M0096
Permit Reviews
Permit Number - T20CM07116
Permit Status: Complete
Permit Description: MFR MTVB290718 T18-M0096
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/15/2020 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 12/01/2020 | COMPLETED |
| 02/15/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/15/2024 | APPROVED |
| 03/01/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/07/2024 | APPROVED |
Conditions
Permit Number - T20CM07116
Permit Status: Complete
Permit Description: MFR MTVB290718 T18-M0096
| Date | Description | Comments |
|---|---|---|
| 10/15/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
| 10/15/2020 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
| 01/03/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 02/15/2024 | ISSUED WITH PDEQ CONDITIONS: NO FINAL AND NO CERTIFICATE OF OCCUPANCY UNTIL THE PRIVATE SEWER #P20SD00114 IS ISSUED A DISCHARGE AUTHORIZATION BY PDEQ | |
| 02/01/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 01/03/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T20CM07116
Permite Description: MFR MTVB290718 T18-M0096
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/22/2021 | COT - RSEL - Electrical Underground | N/A | Canceled | {Activity date: 12/22/2021; Status: Not Applicable; Inspector: DQUINN; Comment: Entered by VVERA1 - na Close permit} ; {Activity date: 02/25/2021; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by VLEON1 - PARTIAL UNDER SLAB CONDUITS OK} ; {Activity date: 02/02/2021; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by VLEON1 - PARTIAL UNDERGOUND TO UNIT OK TO BACKFILL PA IS TO LEAVE INSPECTION OPEN IN CASE IT IS NEEDED FOR ANY UNDER SLAB CONDITIONS} |
Completed Inspections
Permit Status: Complete
Permit Number: T20CM07116
Permit Description: MFR MTVB290718 T18-M0096
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/20/2021 | COT - RSPL - Sewer | Passed | {Activity date: 01/20/2021; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VLEON1 - APPROVED} | |
| 01/20/2021 | COT - RSPL - Rough Soil | Passed | {Activity date: 01/20/2021; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VLEON1 - APPROVED} | |
| 02/25/2021 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 02/25/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VLEON1 - APPROVED} | |
| 02/25/2021 | COT - RSBU - Preslab | Passed | {Activity date: 02/25/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VLEON1 - APPROVED} | |
| 02/25/2021 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 02/25/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VLEON1 - APPROVED} | |
| 04/13/2021 | COT - RSBU - Roof Nailing | Passed | {Activity date: 04/13/2021; Status: Approved; Inspector: RELEFANTE; Comment: Entered by VLEON1 - } | |
| 04/13/2021 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | {Activity date: 04/13/2021; Status: Approved; Inspector: RELEFANTE; Comment: Entered by VLEON1 - } | |
| 05/25/2021 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 05/25/2021; Status: Approved; Inspector: RELEFANTE; Comment: Entered by VLEON1 - } | |
| 05/25/2021 | RSME - Mechanical Progress | Passed | {Activity date: 05/25/2021; Status: Approved; Inspector: RELEFANTE; Comment: Entered by VLEON1 - } | |
| 06/30/2021 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 06/30/2021; Status: Approved; Inspector: RELEFANTE; Comment: Entered by VLEON1 - } | |
| 06/30/2021 | COT - LCBU - Framing | Passed | {Activity date: 06/30/2021; Status: Approved; Inspector: RELEFANTE; Comment: Entered by VLEON1 - } | |
| 06/30/2021 | COT - RSBU - Firewall/Fire Barrier/Firestop | Passed | {Activity date: 06/30/2021; Status: Approved; Inspector: RELEFANTE; Comment: Entered by VLEON1 - } | |
| 08/17/2021 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 08/17/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} ; {Activity date: 08/16/2021; Status: Cancelled; Inspector: RELEFANTE; Comment: Entered by VVERA1 - 1045 cancel Dan called me to cancel because they are not ready } |
|
| 09/01/2021 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 09/01/2021; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - CODE ECO} | |
| 09/01/2021 | COT - RSEL - Construction Power | Passed | {Activity date: 09/01/2021; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved CLEARANCE: ECO} |
|
| 10/06/2021 | COT - RSPL - Yard Water Line | Passed | {Activity date: 10/06/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by RSALDAT1 - Ap} | |
| 12/22/2021 | COT - RSME - Mechanical Final | Passed | {Activity date: 12/22/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap} | |
| 12/22/2021 | COT - RSEL - Outdoor Lighting | Passed | {Activity date: 12/22/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap} | |
| 12/22/2021 | COT - RSPL - Plumbing Final | Passed | {Activity date: 12/22/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap} | |
| 12/22/2021 | COT - RSEL - Electrical Final | Passed | {Activity date: 12/22/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap} | |
| 03/09/2022 | RSBU - Building Final | Passed | {Activity date: 03/09/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by KROBLES1 - } ; {Activity date: 12/22/2021; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by VVERA1 - APPROVED BY INSPECTOR AWAITING CONDITIONS} |