Permit: T20CM06818
Permit Details
Status:
C of o
Type:
COMMERCIAL NEW
Address:
3190 W EL CAMINO DEL CERRO
Address NEW:
3190 W EL CAMINO DEL CERRO
Apply Date:
10/02/2020
Applicant:
METRO TED
Description:
OFFICE/VEHICLE REPAIR
Architects:
- GARCIA DAVID V
Permit Reviews
Permit Number - T20CM06818
Permit Status: C of o
Permit Description: OFFICE/VEHICLE REPAIR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/20/2021 | RESUBMITTAL | 02/02/2021 | COMPLETED |
| 09/28/2020 | COMMERCIAL - NEW | 11/12/2020 | COMPLETED |
| 12/02/2020 | RESUBMITTAL | 01/12/2021 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM06818
Permit Status: C of o
Permit Description: OFFICE/VEHICLE REPAIR
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/02/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T20CM06818
Permit Description: OFFICE/VEHICLE REPAIR
Total Completed Inspections - 26
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/15/2020 | MECHANICAL - FINAL | RSHERRY | Approved | AIR BALANCE REPORT REQUIRED |
| 05/17/2021 | PLUMBING - ROUGH, SOIL | TGAUSP | Approved | |
| 05/24/2021 | ELECTRIC - UNDERGROUND | DQUINN | Approved | Approved - 2 conduits from trans to building, ok to backfill. |
| 05/26/2021 | ELECTRIC - UFER | DQUINN | Approved | Perimeter footing and slab ok to pour. |
| 05/26/2021 | BUILDING PRE-SLAB | DQUINN | Approved | Perimeter footing and slab ok to pour. |
| 10/29/2021 | TEP CLEARANCE - PM | DQUINN | Approved | CODE ECO FOR METER B |
| 10/29/2021 | ELECTRIC - TEMPORARY SERVICE | DQUINN | Approved | Ap |
| 10/29/2021 | ELECTRIC - CONSTRUCTION POWER | DQUINN | Approved | Ap Clear eco for meter B |
| 01/10/2022 | PLUMBING - INTERMEDIATE | DQUINN | Approved | Ap All in-wall and above ceiling ok to cover. |
| 01/24/2022 | ELECTRIC - ABOVE CEILING | DQUINN | Approved | Ap Ok to rock walls. Need Hvac for lids. |
| 01/24/2022 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | Ap |
| 02/07/2022 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | Ap |
| 02/07/2022 | FRAMING | DQUINN | Approved | Ap |
| 02/07/2022 | BUILDING ABOVE CEILING | DQUINN | Approved | Ap |
| 02/07/2022 | U VALUE FOR WINDOW | DQUINN | Approved | Ap |
| 02/07/2022 | BUILDING - PROGRESS | DQUINN | Approved | Ap |
| 07/13/2022 | ELECTRIC - OUTDOOR LIGHTING | TGAUSP | Approved | Approved |
| 07/13/2022 | OUTDOOR LIGHTING FINAL | TGAUSP | Approved | Approved |
| 07/29/2022 | SITE - SEWER | DQUINN | Approved | Ap |
| 07/29/2022 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | Ap |
| 07/29/2022 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | Ap |
| 08/11/2022 | FIRE - FINAL | CGates | Approved | |
| 08/16/2022 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |
| 10/17/2022 | ENGINEERING - FINAL | CTREVIL | Approved | |
| 10/17/2022 | ELECTRIC - FINAL | CTREVIL | Approved | |
| 10/17/2022 | BUILDING - FINAL | CTREVIL | Approved |