Permit: T20CM06734
Permit Details
Apply Date:
09/27/2020
Applicant:
SUNSET WEST CONSTRUCTION LLC
Description:
SFR
Contractors:
- SUNSET WEST CONSTRUCTION LLC
Permit Reviews
Permit Number - T20CM06734
Permit Status: C of o
Permit Description: SFR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/22/2021 | RESUBMITTAL | 02/02/2021 | COMPLETED |
| 02/05/2021 | RESUBMITTAL | 02/16/2021 | COMPLETED |
| 09/23/2020 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 10/28/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM06734
Permit Status: C of o
Permit Description: SFR
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/27/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T20CM06734
Permit Description: SFR
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/16/2021 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | Ap |
| 03/16/2021 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | Ap |
| 03/18/2021 | ELECTRIC - UNDERGROUND | DQUINN | Approved | |
| 03/18/2021 | ELECTRIC - UFER | DQUINN | Approved | |
| 03/18/2021 | BUILDING PRE-SLAB | DQUINN | Approved | |
| 03/18/2021 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | |
| 05/12/2021 | ROOF NAILING | DQUINN | Approved | |
| 05/12/2021 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | |
| 05/21/2021 | TEP CLEARANCE - PM | RELEFANTE | Approved | CODE ECO |
| 05/21/2021 | ELECTRIC - CONSTRUCTION POWER | RELEFANTE | Approved | |
| 05/24/2021 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | |
| 05/24/2021 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
| 05/24/2021 | FRAMING | DQUINN | Approved | |
| 05/24/2021 | RESIDENTIAL INTERMEDIATE | DQUINN | Approved | |
| 07/13/2021 | PLUMBING - SEWER HCS CONNECT | DQUINN | Approved | This was Ap yesterday. 3055 Ap |
| 05/23/2022 | ELECTRIC - FINAL | DQUINN | Approved | Ap |
| 05/23/2022 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | Ap |
| 05/23/2022 | PLUMBING - FINAL | DQUINN | Approved | Ap |
| 05/23/2022 | BUILDING - FINAL | DQUINN | Approved | Ap Close permit |
| 05/23/2022 | MECHANICAL - FINAL | DQUINN | Approved | Ap |
| 05/23/2022 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | Ap |