Permit: T20CM06563
Permit Details
Apply Date:
09/22/2020
Applicant:
MURPHY ROBERT W & ALEXANDRA L JT/RS
Description:
REMODEL; ADD STUDIO
Permit Reviews
Permit Number - T20CM06563
Permit Status: L of c
Permit Description: REMODEL; ADD STUDIO
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/17/2020 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 10/19/2020 | COMPLETED |
10/21/2020 | RESUBMITTAL | 12/01/2020 | COMPLETED |
12/10/2020 | RESUBMITTAL | 12/14/2020 | COMPLETED |
12/14/2020 | RESUBMITTAL | 12/28/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM06563
Permit Status: L of c
Permit Description: REMODEL; ADD STUDIO
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
09/22/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T20CM06563
Permit Description: REMODEL; ADD STUDIO
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/18/2021 | PLUMBING - YARD WTR LINE/TEST | JBURGE | Approved | APPROVED, OK TO COVER PROGRESS AREAS |
04/15/2021 | ELECTRIC - UFER | DQUINN | Approved | NOT READY TEST BALL PROBLEMS ON ROUGH |
05/11/2021 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | Partial. Footing for laundry room and new bathroom. Ok to place concrete in progress area. |
06/02/2021 | PLUMBING - ROUGH, SOIL | JBURGE | Approved | Approved. Ok to cover progress areas. |
08/05/2021 | REINFORCED MASONRY PRE-GROUT | ESTEVENS | Approved | Approved. 4 feet to 9 feet top-out |
09/29/2021 | BUILDING PRE-SLAB | JBURGE | Approved | Approved. Ensure all reinforcement wire mesh is in place. Ok to place concrete in progress areas. |
10/18/2021 | ELECTRIC - FINAL | JBURGE | Approved | Partial. In wall electric complete, lighting in ceiling of studio in place. |
10/22/2021 | FIREWALL/FIREBARRIER/FIRESTOP | JBURGE | Approved | Approved |
11/09/2021 | ROOF NAILING | TGAUSP | Approved | Approved, okay to cover |
12/23/2021 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | pa West side addition elec ok |
12/23/2021 | FRAMING | DQUINN | Approved | pa West side addition frame ok Need fire stop at all top plate penetrations. Inspect fire stop at mech intermediate inspection. |
12/23/2021 | PLUMBING - INTERMEDIATE | DQUINN | Approved | Pa West side addition in-wall pex and abs ok Please re-open 3035. |
12/28/2021 | TEP CLEARANCE - PM | JBURGE | Approved | CODE TMPP |
12/28/2021 | ELECTRIC - CONSTRUCTION POWER | JBURGE | Approved | Approved. Power kill to energize was called in to TEP at 1315 hours CLEARANCE: Code: TMPP |
12/28/2021 | PLUMBING - GAS PRESSURE TEST | JBURGE | Approved | Partial. Pressure test is complete; not ready for meter installation. |
01/04/2022 | ELECTRIC - SERVICE UPGRADE | DMUNIZ | Approved | APPROVED, Clear TEP INCR, Inspection for sub panel feeds approved. Ok to energize and lock out tag out. |
01/11/2022 | GAS CLEARANCE | JBURGE | Approved | CODE |
01/19/2022 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | Approved |
05/10/2022 | OUTDOOR LIGHTING FINAL | JBURGE | Approved | Approved 2090 |
05/10/2022 | PLUMBING - FINAL | JBURGE | Approved | Approved |
08/05/2022 | RESIDENTIAL INTERMEDIATE | JBURGE | Approved | Approved Please close out this permit |
08/05/2022 | BUILDING - FINAL | JBURGE | Approved | Approved Please close out this permit |
08/05/2022 | MECHANICAL - FINAL | JBURGE | Approved | Approved Please close out this permit |