Permit: T20CM06521
Permit Details
Apply Date:
09/21/2020
Applicant:
D R H TUCSON CONSTRUCTION
Description:
SFR DRHO482219 T19-M0151
Contractors:
- D R H TUCSON CONSTRUCTION
Permit Reviews
Permit Number - T20CM06521
Permit Status: Final
Permit Description: SFR DRHO482219 T19-M0151
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/11/2020 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 10/20/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM06521
Permit Status: Final
Permit Description: SFR DRHO482219 T19-M0151
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
09/21/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T20CM06521
Permit Description: SFR DRHO482219 T19-M0151
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/13/2020 | PLUMBING - SEWER HCS CONNECT | DMUNIZ | Approved | Approved |
10/13/2020 | PLUMBING - YARD WTR LINE/TEST | DMUNIZ | Approved | Approved |
10/13/2020 | PLUMBING - ROUGH, SOIL | DMUNIZ | Approved | Approved |
12/08/2020 | TEP CLEARANCE - PM | DMUNIZ | Approved | CODE ECO |
12/08/2020 | ELECTRIC - CONSTRUCTION POWER | DMUNIZ | Approved | Approved clear TEP eco |
12/08/2020 | ELECTRIC - UNDERGROUND | DMUNIZ | Approved | |
12/08/2020 | ELECTRIC - UFER | DMUNIZ | Approved | |
12/08/2020 | BUILDING PRE-SLAB | DMUNIZ | Approved | |
02/12/2021 | ROOF NAILING | WGALLAGHER | Approved | APPROVED |
02/12/2021 | EXT METAL CLIPS/EXT SHEATHING | WGALLAGHER | Approved | APPROVED |
02/12/2021 | EXCAVATION/LAYOUT REBAR & ZON | WGALLAGHER | Approved | APPROVED |
03/31/2021 | GAS CLEARANCE | DMUNIZ | Approved | CODE |
03/31/2021 | PLUMBING - GAS PRESSURE TEST | DMUNIZ | Approved | Approved Clear Southwest Gas |
03/31/2021 | FRAMING | DMUNIZ | Approved | Approved |
03/31/2021 | RESIDENTIAL INTERMEDIATE | DMUNIZ | Approved | Approved |
03/31/2021 | PLUMBING - INTERMEDIATE | DMUNIZ | Approved | Approved |
03/31/2021 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | Approved |
04/13/2021 | SHEET ROCK NAILING | TGAUSP | Approved | |
05/20/2021 | MECHANICAL - FINAL | WGALLAGHER | Approved | |
05/20/2021 | PLUMBING - FINAL | WGALLAGHER | Approved | |
05/20/2021 | OUTDOOR LIGHTING FINAL | WGALLAGHER | Approved | |
05/20/2021 | ELECTRIC - FINAL | WGALLAGHER | Approved | |
05/20/2021 | BUILDING - FINAL | WGALLAGHER | Approved |