Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T20CM06320
Permit Details
Apply Date:
09/14/2020
Applicant:
Steve Olson
Description:
INSTALL NEW AT&T WIRELESS FACILITY
Permit Reviews
Permit Number - T20CM06320
Permit Status: Expired
Permit Description: INSTALL NEW AT&T WIRELESS FACILITY
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/11/2020 | CELL TOWER/ANTENNAS | 11/20/2020 | COMPLETED |
11/30/2020 | CELL TOWER/ANTENNAS | 01/08/2021 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM06320
Permit Status: Expired
Permit Description: INSTALL NEW AT&T WIRELESS FACILITY
Total Outstanding Activity Conditions - 9
Date | Name |
---|---|
09/14/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
10/19/2020 | SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY. |
10/19/2020 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. |
10/19/2020 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. |
10/19/2020 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. |
10/19/2020 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
10/19/2020 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. |
10/19/2020 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. |
10/19/2020 | SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS IS REQUIRED. |
Outstanding Inspections
Permit Status: Expired
Permit Number: T20CM06320
Permite Description: INSTALL NEW AT&T WIRELESS FACILITY
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/07/2022 | COT - LCBU - Building Final | N/A | Canceled | Inspection Canceled |
Completed Inspections
Permit Status: Expired
Permit Number: T20CM06320
Permit Description: INSTALL NEW AT&T WIRELESS FACILITY
Total Completed Inspections - 12
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/14/2021 | COT - LCBU - Excavation/Rebar/Zoning | Passed | {Activity date: 05/14/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VLEON1 - } ; {Activity date: 05/05/2021; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - Partial approval for tower Caisson ok for concrete placement } |
|
05/27/2021 | COT - LCBU - Building Progress | Passed | {Activity date: 05/27/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Approved, final lift complete ok to grout.} ; {Activity date: 05/20/2021; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - Partial approval for 2nd lift of perimeter wall } ; {Activity date: 05/18/2021; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - Partial approval for 1st lift on perimeter wall, ok for concrete placement} |
|
08/03/2021 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 08/03/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - 2090} | |
08/03/2021 | COT - LCBU - Framing | Passed | {Activity date: 08/03/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - 1090} | |
08/03/2021 | COT - LCEL - Electrical Underground | Passed | {Activity date: 08/03/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - 2090} ; {Activity date: 05/19/2021; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - Partial approval for inside perimeter wall ok to backfill} | |
08/03/2021 | COT - LCEL - Outdoor Lighting | Passed | {Activity date: 08/03/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - 2090} | |
08/03/2021 | COT - LCBU - Preslab | Passed | {Activity date: 08/03/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - 1090} | |
08/03/2021 | COT - LCEL - Electrical Final | Passed | {Activity date: 08/03/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved} | |
08/03/2021 | COT - LCEL - Grounding/Bonding | Passed | {Activity date: 08/03/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - 2090} ; {Activity date: 05/19/2021; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - Partial approval for rods, test wells and tower ring, ok to backfill} | |
08/03/2021 | COT - LCBU - Masonry Pregrout | Passed | {Activity date: 08/03/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - 1090} ; {Activity date: 05/05/2021; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - } | |
10/21/2021 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 10/21/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - CODE ECO} | |
10/21/2021 | COT - LCEL - Construction Power | Passed | {Activity date: 10/21/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - APPROVED, CLEAR TEP ECO #1 } |