Permit: T20CM06029
Permit Details
Apply Date:
09/07/2020
Applicant:
SUSAN BHANG
Description:
RETAIL TENANT IMPROVEMENT
Permit Reviews
Permit Number - T20CM06029
Permit Status: C of o
Permit Description: RETAIL TENANT IMPROVEMENT
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/15/2020 | 3RD PARTY REVIEW - COMMERCIAL TI | 10/16/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM06029
Permit Status: C of o
Permit Description: RETAIL TENANT IMPROVEMENT
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
09/07/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T20CM06029
Permit Description: RETAIL TENANT IMPROVEMENT
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/13/2020 | FRAMING | DQUINN | Approved | |
11/19/2020 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | All ductwork ok |
11/19/2020 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | Above lids in changing and bathroom ok. ok to rock. |
11/19/2020 | SHEET ROCK NAILING | DQUINN | Approved | |
12/08/2020 | ENGINEERING - FINAL | BBENEDON | Approved | Not ready. Mall TI with no engineering work. Mark will schedule final inspection when project is complete. NOTE, INSPECTOR FOLLOW UP AND PLACED IN NR. |
12/08/2020 | MECHANICAL - ABOVE CEILING | DQUINN | Approved | |
12/08/2020 | ELECTRIC - PROGRESS | DQUINN | Approved | |
12/08/2020 | ELECTRIC - ABOVE CEILING | DQUINN | Approved | |
12/08/2020 | BUILDING - PROGRESS | DQUINN | Approved | |
12/08/2020 | BUILDING ABOVE CEILING | DQUINN | Approved | |
12/08/2020 | LANDSCAPE - FINAL | BBENEDON | Approved | |
12/08/2020 | NPPO - FINAL | BBENEDON | Approved | |
12/11/2020 | MECHANICAL - FINAL | DQUINN | Approved | |
12/11/2020 | PLUMBING - FINAL | DQUINN | Approved | |
12/11/2020 | ELECTRIC - FINAL | DQUINN | Approved | |
12/11/2020 | BUILDING - FINAL | DQUINN | Approved | 1090 is pa until all other entities are Ap, then Ap 1090, close permit, and issue c of o. |
12/11/2020 | RIGHT OF WAY - FINAL | DR | Approved | NO ROW IMPACT |
12/11/2020 | FIRE - ALARM FINAL | jvincent | Approved | approved by CB on 12/10 |
12/16/2020 | SIGN - FINAL | BBENEDON | Approved | Approved. Mark with Pate construction |
12/16/2020 | FIRE - FINAL | jfordney | Approved | approved via facetime |
12/16/2020 | FIRE SPKLR - FINAL | jfordney | Approved | Approved via facetime |