Permit: T20CM06022
Permit Details
Apply Date:
09/06/2020
Applicant:
MICHAEL PUCKETT
Description:
TENANT IMPROVEMENT: RETAIL PAINT STORE
Architects:
- LINGLE, CARL
Contractors:
- BARKER CONTRACTING INC **APA**
Permit Reviews
Permit Number - T20CM06022
Permit Status: C of o
Permit Description: TENANT IMPROVEMENT: RETAIL PAINT STORE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/12/2020 | COMMERCIAL - TI | 10/30/2020 | COMPLETED |
10/30/2020 | RESUBMITTAL | 12/08/2020 | COMPLETED |
12/14/2020 | RESUBMITTAL | 01/11/2021 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM06022
Permit Status: C of o
Permit Description: TENANT IMPROVEMENT: RETAIL PAINT STORE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
09/06/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T20CM06022
Permit Description: TENANT IMPROVEMENT: RETAIL PAINT STORE
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/29/2020 | PLUMBING - INTERMEDIATE | DQUINN | Approved | PARTIAL, All rough ok to backfill and concrete. Pic of trap primer to be taken. |
12/29/2020 | PLUMBING - INTERMEDIATE | DQUINN | Approved | pa All rough ok to backfill and concrete. Pic of trap primer to be taken. |
01/20/2021 | ELECTRIC - INTERMEDIATE | RBOOHER | Approved | APPROVED |
01/22/2021 | PLUMBING - GAS PRESSURE TEST | ESTEVENS | Approved | CLEAR SWG SUITE 130 |
02/01/2021 | TEP CLEARANCE - PM | RBOOHER | Approved | CODE ECO/SUITE #130 |
02/01/2021 | ELECTRIC - CONSTRUCTION POWER | RBOOHER | Approved | APPROVED |
02/02/2021 | PLUMBING - ABOVE CEILING | RBOOHER | Approved | |
02/25/2021 | MECHANICAL - INTERMEDIATE | TGAUSP | Approved | APPROVED IN ALL AREAS INCLUDING ABOVE CEILING |
03/04/2021 | MECHANICAL - FINAL | DMUNIZ | Approved | |
03/04/2021 | PLUMBING - ROUGH, SOIL | DMUNIZ | Approved | |
03/04/2021 | FRAMING | DMUNIZ | Approved | |
03/15/2021 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |
03/31/2021 | FIRE - FINAL | CBASALDUA | Approved | |
03/31/2021 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
03/31/2021 | ELECTRIC - FINAL | TGAUSP | Approved | |
03/31/2021 | BUILDING - FINAL | TGAUSP | Approved | APPROVED PENDING APPROVAL OF AIR BALANCE/WATER REPORTS |
04/01/2021 | CERTIFICATE OF OCCUPANCY | TGAUSP | Approved | APPROVED OK TO OCCUPY |
04/08/2021 | NPPO - FINAL | DROBERTS | Approved | |
04/08/2021 | RIGHT OF WAY - FINAL | AF | Approved | |
04/08/2021 | U VALUE FOR WINDOW | TGAUSP | Approved | APPROVED STOREFRONT |
04/08/2021 | SIGN - FINAL | MHERNANDEZ | Approved | |
04/08/2021 | ENGINEERING - FINAL | MHERNANDEZ | Approved | |
04/09/2021 | LANDSCAPE - FINAL | DROBERTS | Approved | APPROVED |