Permit Details

Status:
Expired
Type:
Residential Building - One or Two Family
Apply Date:
09/05/2020
Applicant:
Description:
CUSTOM HOME

Permit Reviews

Permit Number - T20CM05994
Permit Status: Expired
Permit Description: CUSTOM HOME
Start Date Submittal Complete Date Status  
08/04/2020 RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO 10/07/2020 COMPLETED Review Details
10/15/2020 RESUBMITTAL 11/09/2020 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T20CM05994
Permit Status: Expired
Permit Description: CUSTOM HOME
Total Outstanding Activity Conditions - 2
Date Name
09/05/2020 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
09/08/2020 ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I)

Outstanding Inspections

Permit Status: Expired
Permit Number: T20CM05994
Permite Description: CUSTOM HOME
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
11/07/2022 RSBU - Building Final N/A Canceled Inspection Canceled

Completed Inspections

Permit Status: Expired
Permit Number: T20CM05994
Permit Description: CUSTOM HOME
Total Completed Inspections - 22
Date Description Inspector Results Comments
11/10/2020 COT - RSPL - Sewer Passed {Activity date: 11/10/2020; Status: Approved; Inspector: DQUINN; Comment: Entered by PAHUMAD1 - }
11/10/2020 COT - RSPL - Rough Soil Passed {Activity date: 11/10/2020; Status: Approved; Inspector: DQUINN; Comment: Entered by PAHUMAD1 - }
11/17/2020 COT - RSEL - Grounding/Bonding Passed {Activity date: 11/17/2020; Status: Approved; Inspector: JBURGE; Comment: Entered by PAHUMAD1 - }
11/17/2020 COT - RSBU - Preslab Passed {Activity date: 11/17/2020; Status: Approved; Inspector: JBURGE; Comment: Entered by PAHUMAD1 - Approved. Ok to place concrete in slab.}
11/17/2020 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 11/17/2020; Status: Approved; Inspector: JBURGE; Comment: Entered by PAHUMAD1 - Approved. Ok to place concrete in footings.}
01/06/2021 COT - RSBU - Roof Nailing Passed {Activity date: 01/06/2021; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VLEON1 - APPROVED} ; {Activity date: 09/08/2020; Status: Prior to Intermediates; Inspector: KEN; Comment: Entered by KKARSEN1 - ROOF TRUSSES MUST BE APPROVED PRIOR TO INSPECTION}
01/20/2021 COT - RSBU - Exterior Clips/Sheathing Passed {Activity date: 01/20/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VLEON1 - APPROVED} ; {Activity date: 01/06/2021; Status: Not ready for Inspection; Inspector: ESTEVENS; Comment: Entered by VLEON1 - }
02/10/2021 COT - LCBU - Framing Passed {Activity date: 02/10/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VLEON1 - APPROVED}
02/10/2021 COT - LCPL - Plumbing Intermediate Passed {Activity date: 02/10/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VLEON1 - APPROVED}
02/10/2021 COT - BULD - SWG Clearance Passed {Activity date: 02/10/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VLEON1 - CODE}
02/10/2021 RSEL - Electrical Progress Passed {Activity date: 02/10/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VLEON1 - APPROVED}
02/10/2021 RSME - Mechanical Progress Passed {Activity date: 02/10/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VLEON1 - APPROVED}
02/10/2021 COT - RSPL - Gas Pressure Test Passed {Activity date: 02/10/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VLEON1 - APPROVED}
05/14/2021 COT - RSPL - Yard Water Line Passed {Activity date: 05/14/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VLEON1 - }
05/14/2021 COT - RSEL - Electrical Underground Passed {Activity date: 05/14/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VLEON1 - APPROVED UNDER SLAB CONDUIT}
06/08/2021 PDSD Building Division - TEP PM Clearance Passed {Activity date: 06/08/2021; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VLEON1 - CODE INCR/CUTOVER}
06/08/2021 COT - RSEL - Construction Power Passed {Activity date: 06/08/2021; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VLEON1 - } ; {Activity date: 06/03/2021; Status: Not ready for Inspection; Inspector: TGAUSP; Comment: Entered by VLEON1 - NR, Missing water and gas bonds.

}
09/01/2021 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed {Activity date: 09/01/2021; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - Approved

Please close out this permit.}
09/01/2021 COT - RSME - Mechanical Final Passed {Activity date: 09/01/2021; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - Approved

Please close out this permit.}
09/01/2021 COT - RSEL - Outdoor Lighting Passed {Activity date: 09/01/2021; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - Approved

Please close out this permit.}
09/01/2021 COT - RSPL - Plumbing Final Passed {Activity date: 09/01/2021; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - Approved

Please close out this permit.}
09/01/2021 COT - RSEL - Electrical Final Passed {Activity date: 09/01/2021; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - Approved

Please close out this permit.}

Documents

File Name Document Type  
PLAN SET.PDF CONSTRPLANS VIEW
APPLICATION.PDF DOCUMENTS VIEW
STRUCTURAL CALCULATIONS.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW