Permit: T20CM05941
Permit Details
Apply Date:
09/04/2020
Applicant:
TECHNICIANS FOR SUSTAINABILITY INC
Description:
392.04 kW DC PV SYSTEM ON 3 STEEL CANOPIES
Contractors:
- TECHNICIANS FOR SUSTAINABILITY INC
Permit Reviews
Permit Number - T20CM05941
Permit Status: Final
Permit Description: 392.04 kW DC PV SYSTEM ON 3 STEEL CANOPIES
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/04/2020 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 10/28/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM05941
Permit Status: Final
Permit Description: 392.04 kW DC PV SYSTEM ON 3 STEEL CANOPIES
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
09/04/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T20CM05941
Permit Description: 392.04 kW DC PV SYSTEM ON 3 STEEL CANOPIES
Total Completed Inspections - 12
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/16/2020 | ELECTRIC - UFER | ESTEVENS | Approved | |
12/15/2020 | ELECTRIC - UNDERGROUND | DQUINN | Approved | Underground from P1 to transformer and electrical room, along with transformer ufer, ok to backfill. Also, from P2 to just shy of P1 ok to backfill. |
12/30/2020 | EXCAVATION/LAYOUT REBAR & ZON | RBOOHER | Approved | Approved... Verified Ufer and footer depth..Ok to pour footers for Steel Structural posts. |
02/02/2021 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | APPROVED ELECTRIC ROOM CAN SETUP OK TO PULL WIRE |
02/08/2021 | ELECTRIC - SERVICE UPGRADE | ESTEVENS | Approved | CODE DGL |
02/17/2021 | TEP CLEARANCE - PM | TGAUSP | Approved | CODE DGL/DGC |
02/17/2021 | ELECTRIC - OUTDOOR LIGHTING | TGAUSP | Approved | APPROVED |
02/17/2021 | ELECTRIC - TEMPORARY SERVICE | TGAUSP | Approved | APPROVED |
02/17/2021 | BUILDING - PROGRESS | TGAUSP | Approved | APPROVED |
02/17/2021 | ELECTRIC - FINAL | TGAUSP | Approved | APPROVED |
02/17/2021 | OUTDOOR LIGHTING FINAL | TGAUSP | Approved | APPROVED |
02/17/2021 | BUILDING - FINAL | TGAUSP | Approved | APPROVED |