Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
09/03/2020
Applicant:
Description:
INSTALLATION OF (6) NEW ANTENNAS, (6) RRHS, (2) OPV 12 BOX BEHIND NEW FPR SCREEN AND ABOVE EXISTING

Permit Reviews

Permit Number - T20CM05909
Permit Status: Complete
Permit Description: INSTALLATION OF (6) NEW ANTENNAS, (6) RRHS, (2) OPV 12 BOX BEHIND NEW FPR SCREEN AND ABOVE EXISTING
Start Date Submittal Complete Date Status  
08/26/2020 CELL TOWER/ANTENNAS 10/21/2020 COMPLETED Review Details

Conditions

Permit Number - T20CM05909
Permit Status: Complete
Permit Description: INSTALLATION OF (6) NEW ANTENNAS, (6) RRHS, (2) OPV 12 BOX BEHIND NEW FPR SCREEN AND ABOVE EXISTING
Date Description Comments
09/03/2020 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
05/24/2022 SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY.
10/20/2020 SPECIAL INSPECTION FOR CONCRETE IS REQUIRED..
10/20/2020 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: T20CM05909
Permite Description: INSTALLATION OF (6) NEW ANTENNAS, (6) RRHS, (2) OPV 12 BOX BEHIND NEW FPR SCREEN AND ABOVE EXISTING
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
10/27/2022 COT - LCBU - Building Final N/A Not Ready

Completed Inspections

Permit Status: Complete
Permit Number: T20CM05909
Permit Description: INSTALLATION OF (6) NEW ANTENNAS, (6) RRHS, (2) OPV 12 BOX BEHIND NEW FPR SCREEN AND ABOVE EXISTING
Total Completed Inspections - 7
Date Description Inspector Results Comments
09/14/2021 COT - LCBU - Excavation/Rebar/Zoning Passed {Activity date: 09/14/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP including ufer}
09/17/2021 COT - LCBU - Masonry Pregrout Passed {Activity date: 09/17/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved ok to grout}
10/14/2021 COT - LCEL - Electrical Underground Passed {Activity date: 10/14/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -AP. 2090} ; {Activity date: 09/09/2021; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Partial approval for sweeps and under slab ok to backfill}
10/14/2021 PDSD Building Division - TEP PM Clearance Passed {Activity date: 10/14/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - CODE ECO}
10/14/2021 COT - LCEL - Electrical Final Passed {Activity date: 10/14/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -AP. ECO clearance for TEP.}
10/14/2021 COT - LCEL - Service Upgrade Passed {Activity date: 10/14/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -AP 2090} ; {Activity date: 09/09/2021; Status: Not ready for Inspection; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Not ready}
06/07/2023 COT - LCBU - Building Final Passed

Documents

File Name Document Type  
2022-05-18 - UPDATE TO T20CM05909.PDF DOCUMENTS VIEW
SIC.PDF DOCUMENTS VIEW