Permit: T20CM05771
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
969 W COVENTRY PL UNIT 1
Address NEW:
969 W COVENTRY PL UNIT 1
Apply Date:
09/01/2020
Applicant:
Description:
DUPLEX SWDUPLEXM 969 W COVENTRY PL
Conditions
Permit Number - T20CM05771
Permit Status: Complete
Permit Description: DUPLEX SWDUPLEXM 969 W COVENTRY PL
| Date | Description | Comments |
|---|---|---|
| 09/01/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
| 09/01/2020 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
Completed Inspections
Permit Status: Complete
Permit Number: T20CM05771
Permit Description: DUPLEX SWDUPLEXM 969 W COVENTRY PL
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/15/2020 | COT - RSPL - Rough Soil | Passed | {Activity date: 12/15/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VLEON1 - APPROVED} ; {Activity date: 12/15/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VLEON1 - APPROVED} | |
| 12/17/2020 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 12/17/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VLEON1 - APPROVED} | |
| 12/17/2020 | COT - RSBU - Preslab | Passed | {Activity date: 12/17/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VLEON1 - APPROVED} | |
| 12/17/2020 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 12/17/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VLEON1 - APPROVED} | |
| 01/20/2021 | COT - RSBU - Roof Nailing | Passed | {Activity date: 01/20/2021; Status: Approved; Inspector: RBOOHER; Comment: Entered by RSALDAT1 - Approved.....} | |
| 01/20/2021 | COT - LCBU - Framing | Passed | {Activity date: 01/20/2021; Status: Approved; Inspector: RBOOHER; Comment: Entered by RSALDAT1 - Approved.....} | |
| 01/20/2021 | COT - RSBU - Firewall/Fire Barrier/Firestop | Passed | {Activity date: 01/20/2021; Status: Approved; Inspector: RBOOHER; Comment: Entered by RSALDAT1 - Approved.....} | |
| 01/20/2021 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | {Activity date: 01/20/2021; Status: Approved; Inspector: RBOOHER; Comment: Entered by RSALDAT1 - Approved.....} | |
| 02/04/2021 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 02/04/2021; Status: Approved; Inspector: KCOCO; Comment: Entered by VLEON1 - .approved. UFFER ground was also inspected and approved. All prior comments for intermediate have been addressed and corrected as noted. } ; {Activity date: 02/03/2021; Status: Partial Approval; Inspector: RBOOHER; Comment: Entered by VLEON1 - PARTIAL - UNIT #1 FOLLOWING ITEMS..ADA BACKING, BRACE FOR REGISTER, TRAP LAUNDRY ROOM AND UNIT #2 NOT READY} ; {Activity date: 02/01/2021; Status: Not ready for Inspection; Inspector: RBOOHER; Comment: Entered by VLEON1 - NOT READY RESCHEDULE} |
|
| 03/11/2021 | COT - RSPL - Sewer | Passed | {Activity date: 03/11/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VLEON1 - } | |
| 03/12/2021 | COT - RSPL - Yard Water Line | Passed | {Activity date: 03/12/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VLEON1 - } ; {Activity date: 03/11/2021; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by VLEON1 - } | |
| 08/10/2021 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 08/10/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - CODE ECO/UNITS 1 & 2} | |
| 08/10/2021 | COT - RSEL - Construction Power | Passed | {Activity date: 08/10/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - - Approved, please send ECO Clearance to TEP for construction power (units #1,#2)} | |
| 09/17/2021 | COT - RSME - Mechanical Final | Passed | {Activity date: 09/17/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved for units 1 and 2} | |
| 09/17/2021 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 09/17/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved with 1080} | |
| 09/17/2021 | COT - RSEL - Outdoor Lighting | Passed | {Activity date: 09/17/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved for units 1 and 2} | |
| 09/17/2021 | COT - RSPL - Plumbing Final | Passed | {Activity date: 09/17/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved for units 1 and 2} | |
| 09/17/2021 | RSME - Mechanical Progress | Passed | {Activity date: 09/17/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved with 1080} | |
| 09/17/2021 | COT - RSEL - Electrical Final | Passed | {Activity date: 09/17/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved for units 1 and 2} | |
| 11/07/2022 | RSBU - Building Final | Passed | Inspection Canceled 1/22/24 conditions satisfied |