Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T20CM05628
Permit Details
Apply Date:
08/29/2020
Applicant:
N/A
Description:
INTERIOR RENOVATIONS TO AN EXISTING LAUNDROMAT
Contractors:
- MW MORRISSEY CONSTRUCTION LLC
Permit Reviews
Permit Number - T20CM05628
Permit Status: L of c
Permit Description: INTERIOR RENOVATIONS TO AN EXISTING LAUNDROMAT
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/30/2020 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 09/26/2020 | COMPLETED |
10/05/2020 | RESUBMITTAL | 10/21/2020 | COMPLETED |
10/23/2020 | RESUBMITTAL | 11/24/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM05628
Permit Status: L of c
Permit Description: INTERIOR RENOVATIONS TO AN EXISTING LAUNDROMAT
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
08/29/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T20CM05628
Permit Description: INTERIOR RENOVATIONS TO AN EXISTING LAUNDROMAT
Total Completed Inspections - 13
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/29/2020 | MECHANICAL - FINAL | RSHERRY | Approved | AIR BALANCE REPORT REQUIRED |
10/29/2020 | PLUMBING - FINAL | RSHERRY | Approved | WATER DISINFECTION REPORT REQUIRED |
11/27/2020 | PLUMBING - ROUGH, SOIL | TTREMBULAK | Approved | Approved |
12/02/2020 | FRAMING | ESTEVENS | Approved | Partial. Sister roof trusses only. |
12/17/2020 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | Ap Ok to rock hard lid and install drop grid. |
12/17/2020 | PLUMBING - INTERMEDIATE | DQUINN | Approved | Ap Ok to rock hard lid and install drop grid. |
12/17/2020 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | Ap Ok to rock hard lid and install drop grid. |
01/12/2021 | ELECTRIC - ABOVE CEILING | ESTEVENS | Approved | APPROVED |
01/12/2021 | BUILDING ABOVE CEILING | ESTEVENS | Approved | APPROVED |
01/25/2021 | FIRE - FINAL | CBASALDUA | Approved | |
01/25/2021 | ENGINEERING - FINAL | DROBERTS | Approved | APPROVED |
01/26/2021 | ELECTRIC - FINAL | TGAUSP | Approved | APPROVED, PENDING HT0 DISINFECTION REPORT |
01/26/2021 | BUILDING - FINAL | TGAUSP | Approved | APPROVED |