Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Final
Type:
SINGLE FAMILY NEW
Address NEW:
1300 S SAN FELIPE DR
Apply Date:
08/07/2020
Applicant:
RODRIGO SALAZAR - R&R GENERAL CONTRACTING LLC
Description:
E - SFR MODEL100 T20-M0007
Contractors:
  • R&R GENERAL CONTRACTING LLC

Permit Reviews

Permit Number - T20CM05124
Permit Status: Final
Permit Description: E - SFR MODEL100 T20-M0007
Start Date Submittal Complete Date Status  
08/07/2020 RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO 08/27/2020 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T20CM05124
Permit Status: Final
Permit Description: E - SFR MODEL100 T20-M0007
Total Outstanding Activity Conditions - 1
Date Name
08/07/2020 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T20CM05124
Permit Description: E - SFR MODEL100 T20-M0007
Total Completed Inspections - 20
Date Description Inspector Results Comments
10/05/2020 PLUMBING - ROUGH, SOIL DMUNIZ Approved
10/09/2020 ELECTRIC - UFER ESTEVENS Approved All three are approved.
10/09/2020 BUILDING PRE-SLAB ESTEVENS Approved All three are approved.
10/09/2020 EXCAVATION/LAYOUT REBAR & ZON ESTEVENS Approved All three are approved.
10/30/2020 PLUMBING - SEWER HCS CONNECT DQUINN Approved Ap
11/06/2020 ROOF NAILING JBURGE Approved Approved. Ok to dry-in roof system.
11/06/2020 EXT METAL CLIPS/EXT SHEATHING JBURGE Approved Approved.
11/18/2020 MECHANICAL - INTERMEDIATE ESTEVENS Approved
11/18/2020 PLUMBING - INTERMEDIATE ESTEVENS Approved
11/18/2020 RESIDENTIAL INTERMEDIATE ESTEVENS Approved
11/18/2020 FRAMING ESTEVENS Approved
12/02/2020 TEP CLEARANCE - PM ESTEVENS Approved CODE ECO
12/02/2020 SHEET ROCK NAILING ESTEVENS Approved The TEP clearance code is ECO
12/30/2020 PLUMBING - YARD WTR LINE/TEST DMUNIZ Approved APPROVED
02/25/2021 MECHANICAL - FINAL TGAUSP Approved APPROVED
02/25/2021 PLUMBING - FINAL TGAUSP Approved APPROVED
02/25/2021 OUTDOOR LIGHTING FINAL TGAUSP Approved APPROVED
02/25/2021 ELECTRIC - CONSTRUCTION POWER TGAUSP Approved APPROVED INSPECTOR DID NOT REQUEST A TEP CLEARANCE
02/25/2021 BUILDING - FINAL TGAUSP Approved APPROVED
02/25/2021 ELECTRIC - FINAL TGAUSP Approved APPROVED

Documents

File Name Document Type  
TRUSSES.PDF DOCUMENTS VIEW
SITE PLAN.PDF CONSTRPLANS VIEW