Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Expired
Type:
Residential Building - One or Two Family
Address NEW:
2002 S ROSEMONT AV
Apply Date:
08/03/2020
Applicant:
Description:
ADDITIONAL ROOM BEING TURNED INTO A LAUNDRY ROOM

Permit Reviews

Permit Number - T20CM04986
Permit Status: Expired
Permit Description: ADDITIONAL ROOM BEING TURNED INTO A LAUNDRY ROOM
Start Date Submittal Complete Date Status  
04/21/2021 REVISION - - 1ST 04/23/2021 COMPLETED Review Details
06/29/2020 RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO 12/03/2020 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T20CM04986
Permit Status: Expired
Permit Description: ADDITIONAL ROOM BEING TURNED INTO A LAUNDRY ROOM
Total Outstanding Activity Conditions - 1
Date Name
08/03/2020 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Outstanding Inspections

Permit Status: Expired
Permit Number: T20CM04986
Permite Description: ADDITIONAL ROOM BEING TURNED INTO A LAUNDRY ROOM
Total Outstanding Inspections - 5
Last Inspection Date Description Inspector Results Comments
04/01/2022 COT - RSPL - Sewer N/A Canceled {Activity date: 04/01/2022; Status: Not Applicable; Inspector: RCHANDLER; Comment: Entered by VVERA1 - NA} ; {Activity date: 03/11/2022; Status: Denied; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Not inspected}
11/04/2022 COT - RSME - Mechanical Final N/A Canceled Inspection Canceled
11/04/2022 RSBU - Building Final N/A Canceled Inspection Canceled
11/04/2022 COT - RSPL - Plumbing Final N/A Canceled Inspection Canceled
11/04/2022 COT - RSEL - Electrical Final N/A Canceled Inspection Canceled

Completed Inspections

Permit Status: Expired
Permit Number: T20CM04986
Permit Description: ADDITIONAL ROOM BEING TURNED INTO A LAUNDRY ROOM
Total Completed Inspections - 10
Date Description Inspector Results Comments
03/11/2022 COT - RSBU - Roof Nailing Passed {Activity date: 03/11/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved

}
03/11/2022 COT - RSBU - Preslab Passed {Activity date: 03/11/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved

}
03/11/2022 COT - RSPL - Rough Soil Passed {Activity date: 03/11/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved

}
03/11/2022 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 03/11/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved

}
03/29/2022 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed {Activity date: 03/29/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP}
04/01/2022 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed {Activity date: 04/01/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 03/29/2022; Status: Denied; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -DE. No answer at door at 12:08PM.} ; {Activity date: 03/11/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Partial approval please provide split ground and neutral bus’s for sub panel}
04/01/2022 COT - LCBU - Framing Passed {Activity date: 04/01/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP}
04/01/2022 COT - LCPL - Plumbing Intermediate Passed {Activity date: 04/01/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 03/29/2022; Status: Denied; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -DE. No answer at door at 12:08PM.} ; {Activity date: 03/11/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Partial approval please correct washer drain/p-trap/venting}
04/01/2022 RSEL - Electrical Progress Passed {Activity date: 04/01/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 03/11/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Partial approval please connect all grounds together in electrical boxes and ground exterior light box}
04/01/2022 RSME - Mechanical Progress Passed {Activity date: 04/01/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 03/29/2022; Status: Denied; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -DE. No answer at door at 12:08PM.} ; {Activity date: 03/11/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Partial approval Block registers on 3 sides and exhaust fans must be ducted outside}

Documents

File Name Document Type  
APPLICATION 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
JOB CARD 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PERMIT 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PLAN SET 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
PLAN SET.PDF DOCUMENTS VIEW