Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T20CM04934
Permit Details
Apply Date:
07/31/2020
Applicant:
HELEN ORMSBY
Description:
SFR DRHRTN3548 T19-M0072
Contractors:
- D R H TUCSON CONSTRUCTION
Permit Reviews
Permit Number - T20CM04934
Permit Status: Final
Permit Description: SFR DRHRTN3548 T19-M0072
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/31/2020 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 09/06/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM04934
Permit Status: Final
Permit Description: SFR DRHRTN3548 T19-M0072
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
07/31/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T20CM04934
Permit Description: SFR DRHRTN3548 T19-M0072
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/26/2020 | PLUMBING - ROUGH, SOIL | ESTEVENS | Approved | All three are approved. |
08/26/2020 | PLUMBING - YARD WTR LINE/TEST | ESTEVENS | Approved | All three are approved. |
08/26/2020 | PLUMBING - SEWER HCS CONNECT | ESTEVENS | Approved | All three are approved. |
09/29/2020 | TEP CLEARANCE - PM | ESTEVENS | Approved | CODE ECO |
09/29/2020 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVENS | Approved | All five are approved. The TEP clearance code is ECO. |
09/29/2020 | BUILDING PRE-SLAB | ESTEVENS | Approved | All five are approved. The TEP clearance code is ECO. |
09/29/2020 | ELECTRIC - UFER | ESTEVENS | Approved | All five are approved. The TEP clearance code is ECO. |
09/29/2020 | ELECTRIC - UNDERGROUND | ESTEVENS | Approved | All five are approved. The TEP clearance code is ECO. |
09/29/2020 | ELECTRIC - CONSTRUCTION POWER | ESTEVENS | Approved | All five are approved. The TEP clearance code is ECO. |
10/30/2020 | ROOF NAILING | DQUINN | Approved | Ap |
10/30/2020 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | Ap |
12/02/2020 | GAS CLEARANCE | DQUINN | Approved | CODE |
12/02/2020 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | Clear gas |
12/02/2020 | RESIDENTIAL INTERMEDIATE | DQUINN | Approved | |
12/15/2020 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | Ap |
12/15/2020 | PLUMBING - INTERMEDIATE | DQUINN | Approved | Ap |
12/15/2020 | SHEET ROCK NAILING | DQUINN | Approved | Ap |
01/27/2021 | MECHANICAL - FINAL | DQUINN | Approved | APPROVED |
01/27/2021 | PLUMBING - FINAL | DQUINN | Approved | APPROVED |
01/27/2021 | ELECTRIC - FINAL | DQUINN | Approved | APPROVED |
01/27/2021 | FRAMING | DQUINN | Approved | APPROVED |
02/01/2021 | BUILDING - FINAL | DQUINN | Approved | CONDITIONS SATISFIED |