Permit: T20CM04832
Permit Details
Apply Date:
07/28/2020
Applicant:
CORNERSTONE CONTRACTORS INC
Description:
NEW SFR CORN150019 T19-M0094
Contractors:
- CORNERSTONE CONTRACTORS INC
Permit Reviews
Permit Number - T20CM04832
Permit Status: Final
Permit Description: NEW SFR CORN150019 T19-M0094
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/12/2020 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 08/04/2020 | COMPLETED |
| 09/25/2020 | RESUBMITTAL | 10/19/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM04832
Permit Status: Final
Permit Description: NEW SFR CORN150019 T19-M0094
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/28/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T20CM04832
Permit Description: NEW SFR CORN150019 T19-M0094
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/12/2020 | ROOF NAILING | TVALENCIA | Approved | Both are approved. |
| 08/12/2020 | EXT METAL CLIPS/EXT SHEATHING | TVALENCIA | Approved | Both are approved. |
| 09/17/2020 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | |
| 09/17/2020 | RESIDENTIAL INTERMEDIATE | DQUINN | Approved | Ap |
| 09/17/2020 | FRAMING | DQUINN | Approved | Ap |
| 09/17/2020 | PLUMBING - INTERMEDIATE | DQUINN | Approved | Ap |
| 09/17/2020 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | Ap |
| 09/30/2020 | SHEET ROCK NAILING | DQUINN | Approved | Ap |
| 10/27/2020 | TEP CLEARANCE - PM | DQUINN | Approved | CODE ECO |
| 10/27/2020 | ELECTRIC - CONSTRUCTION POWER | DQUINN | Approved | Ap Clear eco |
| 12/03/2020 | PLUMBING - SEWER HCS CONNECT | BSTEVENS | Approved | BASED ON QUALITY OF WORK AT OTHER ADDRESSES I AM APPROVING THE ROUGH PLUMBING |
| 12/03/2020 | PLUMBING - YARD WTR LINE/TEST | BSTEVENS | Approved | BASED ON QUALITY OF WORK AT OTHER ADDRESSES I AM APPROVING THE ROUGH PLUMBING |
| 12/03/2020 | PLUMBING - ROUGH, SOIL | BSTEVENS | Approved | BASED ON QUALITY OF WORK AT OTHER ADDRESSES I AM APPROVING THE ROUGH PLUMBING |
| 12/03/2020 | ELECTRIC - UNDERGROUND | BSTEVENS | Approved | INSPECTIONS WERE OVERLOOKED DURING THE ABSENSE OF THE SUPERINTENDENT. BASED ON QUALITY OF WORK ON OTHER HOMES, I AM APPROVING THIS PRE-SLAB INSPECTION. |
| 12/03/2020 | ELECTRIC - UFER | BSTEVENS | Approved | INSPECTIONS WERE OVERLOOKED DURING THE ABSENSE OF THE SUPERINTENDENT. BASED ON QUALITY OF WORK ON OTHER HOMES, I AM APPROVING THIS PRE-SLAB INSPECTION. |
| 12/03/2020 | BUILDING PRE-SLAB | BSTEVENS | Approved | INSPECTIONS WERE OVERLOOKED DURING THE ABSENSE OF THE SUPERINTENDENT. BASED ON QUALITY OF WORK ON OTHER HOMES, I AM APPROVING THIS PRE-SLAB INSPECTION. |
| 12/03/2020 | EXCAVATION/LAYOUT REBAR & ZON | BSTEVENS | Approved | INSPECTIONS WERE OVERLOOKED DURING THE ABSENSE OF THE SUPERINTENDENT. BASED ON QUALITY OF WORK ON OTHER HOMES, I AM APPROVING THIS PRE-SLAB INSPECTION. |
| 12/16/2020 | BUILDING - FINAL | DQUINN | Approved | Ap FEE BAL |
| 12/16/2020 | ELECTRIC - FINAL | DQUINN | Approved | Ap |
| 12/16/2020 | PLUMBING - FINAL | DQUINN | Approved | Ap |
| 12/16/2020 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | Ap |
| 12/16/2020 | MECHANICAL - FINAL | DQUINN | Approved | Ap |