Permit: T20CM04712
Permit Details
Status:
Expired
Type:
Residential Building - One or Two Family
Address:
6858 E VIA ARROYO LARGO
Address NEW:
6858 E VIA ARROYO LARGO
Apply Date:
07/23/2020
Applicant:
Description:
SFR LENN400319 T19-M0122
Outstanding Activity Conditions
Permit Number - T20CM04712
Permit Status: Expired
Permit Description: SFR LENN400319 T19-M0122
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 07/23/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
| 07/23/2020 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
| 07/23/2020 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
Outstanding Inspections
Permit Status: Expired
Permit Number: T20CM04712
Permite Description: SFR LENN400319 T19-M0122
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/07/2022 | RSBU - Building Final | N/A | Canceled | Inspection Canceled |
Completed Inspections
Permit Status: Expired
Permit Number: T20CM04712
Permit Description: SFR LENN400319 T19-M0122
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/27/2020 | COT - RSPL - Yard Water Line | Passed | {Activity date: 08/27/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by RSALDAT1 - Approved} | |
| 08/27/2020 | COT - RSPL - Sewer | Passed | {Activity date: 08/27/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by RSALDAT1 - Approved} | |
| 08/27/2020 | COT - RSPL - Rough Soil | Passed | {Activity date: 08/27/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by RSALDAT1 - Approved} | |
| 09/08/2020 | COT - RSBU - Preslab | Passed | {Activity date: 09/08/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by JSCHNEI2 - Approved} |
|
| 09/08/2020 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 09/08/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by JSCHNEI2 - Approved} |
|
| 09/29/2020 | COT - RSBU - Roof Nailing | Passed | {Activity date: 09/29/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} | |
| 09/29/2020 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | {Activity date: 09/29/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} | |
| 11/13/2020 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 11/13/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by PAHUMAD1 - } | |
| 11/13/2020 | COT - LCBU - Framing | Passed | {Activity date: 11/13/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by PAHUMAD1 - } | |
| 11/13/2020 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 11/13/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by PAHUMAD1 - } | |
| 11/13/2020 | RSME - Mechanical Progress | Passed | {Activity date: 11/13/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by PAHUMAD1 - } | |
| 11/13/2020 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 11/13/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by PAHUMAD1 - } ; {Activity date: 08/27/2020; Status: Cancelled; Inspector: TTREMBULAK; Comment: Entered by RSALDAT1 - Cancelled by contractor.} | |
| 11/25/2020 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 11/25/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved} | |
| 01/15/2021 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 01/15/2021; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by VLEON1 - CODE ECO} | |
| 01/15/2021 | COT - RSEL - Construction Power | Passed | {Activity date: 01/15/2021; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by VLEON1 - APPROVED} ; {Activity date: 09/09/2020; Status: Cancelled; Inspector: TTREMBULAK; Comment: Entered by RSALDAT1 - Cancelled by contractor. Will reschedule.} ; {Activity date: 09/08/2020; Status: Cancelled; Inspector: TTREMBULAK; Comment: Entered by JSCHNEI2 - Cancelled by contractor} | |
| 02/22/2021 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 02/22/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - APPROVED} ; {Activity date: 09/09/2020; Status: Cancelled; Inspector: TTREMBULAK; Comment: Entered by RSALDAT1 - Cancelled by contractor. Will reschedule.} ; {Activity date: 09/08/2020; Status: Partial Approval; Inspector: TTREMBULAK; Comment: Entered by JSCHNEI2 - Partial. Ok to pour slab. } |
|
| 02/22/2021 | COT - RSME - Mechanical Final | Passed | {Activity date: 02/22/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - APPROVED} | |
| 02/22/2021 | COT - RSEL - Outdoor Lighting | Passed | {Activity date: 02/22/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - APPROVED} ; {Activity date: 11/25/2020; Status: Not ready for Inspection; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Not ready} | |
| 02/22/2021 | COT - RSPL - Plumbing Final | Passed | {Activity date: 02/22/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - APPROVED} | |
| 02/22/2021 | COT - RSEL - Electrical Final | Passed | {Activity date: 02/22/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - APPROVED} |