Permit: T20CM04643
Permit Details
Status:
Expired
Type:
Residential Building - One or Two Family
Address:
7252 S VIA GAUCHO VIEJO
Address NEW:
7252 S VIA GAUCHO VIEJO
Apply Date:
07/22/2020
Applicant:
Dana Petty
Description:
SFR MERI2380A19 T19-M0160
Outstanding Activity Conditions
Permit Number - T20CM04643
Permit Status: Expired
Permit Description: SFR MERI2380A19 T19-M0160
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 07/22/2020 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
| 07/22/2020 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
Outstanding Inspections
Permit Status: Expired
Permit Number: T20CM04643
Permite Description: SFR MERI2380A19 T19-M0160
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/07/2022 | RSBU - Building Final | N/A | Canceled | Inspection Canceled |
Completed Inspections
Permit Status: Expired
Permit Number: T20CM04643
Permit Description: SFR MERI2380A19 T19-M0160
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/16/2020 | COT - RSPL - Sewer | Passed | {Activity date: 09/16/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by JSCHNEI2 - Approved} | |
| 09/16/2020 | COT - RSPL - Rough Soil | Passed | {Activity date: 09/16/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by JSCHNEI2 - Approved} | |
| 09/28/2020 | COT - RSBU - Preslab | Passed | {Activity date: 09/28/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by RSALDAT1 - Approved} | |
| 09/28/2020 | COT - RSEL - Electrical Underground | Passed | {Activity date: 09/28/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by RSALDAT1 - Approved} | |
| 09/28/2020 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 09/28/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by RSALDAT1 - Approved} | |
| 10/26/2020 | COT - RSBU - Roof Nailing | Passed | {Activity date: 10/26/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved} | |
| 10/26/2020 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | {Activity date: 10/26/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved} | |
| 11/04/2020 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 11/04/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by PAHUMAD1 - CODE ECO} | |
| 11/04/2020 | COT - RSEL - Construction Power | Passed | {Activity date: 11/04/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by PAHUMAD1 - Approved ok for clearance eco} | |
| 12/16/2020 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 12/16/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} ; {Activity date: 12/11/2020; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by PAHUMAD1 - Inspection canceled by contractor } |
|
| 12/16/2020 | COT - LCBU - Framing | Passed | {Activity date: 12/16/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} ; {Activity date: 12/11/2020; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by PAHUMAD1 - Inspection canceled by contractor } |
|
| 12/16/2020 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 12/16/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} ; {Activity date: 12/11/2020; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by PAHUMAD1 - Inspection canceled by contractor } |
|
| 12/16/2020 | COT - BULD - SWG Clearance | Passed | {Activity date: 12/16/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - CODE} | |
| 12/16/2020 | RSME - Mechanical Progress | Passed | {Activity date: 12/16/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} ; {Activity date: 12/11/2020; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by PAHUMAD1 - Inspection canceled by contractor } |
|
| 12/16/2020 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 12/16/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved Clear Southwest gas} ; {Activity date: 12/11/2020; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by PAHUMAD1 - Inspection canceled by contractor } |
|
| 01/27/2021 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 01/27/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - APPROVED} | |
| 03/18/2021 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 03/18/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - } ; {Activity date: 09/28/2020; Status: Partial Approval; Inspector: TTREMBULAK; Comment: Entered by RSALDAT1 - Partial. Ok to pour slab.} | |
| 03/18/2021 | COT - RSME - Mechanical Final | Passed | {Activity date: 03/18/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - } | |
| 03/18/2021 | COT - RSPL - Yard Water Line | Passed | {Activity date: 03/18/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - } ; {Activity date: 09/16/2020; Status: Partial Approval; Inspector: TTREMBULAK; Comment: Entered by JSCHNEI2 - Partial. Ok to backfill, no meter at this time.} | |
| 03/18/2021 | COT - RSEL - Outdoor Lighting | Passed | {Activity date: 03/18/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - } ; {Activity date: 03/18/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - } | |
| 03/18/2021 | COT - RSPL - Plumbing Final | Passed | {Activity date: 03/18/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - } ; {Activity date: 03/18/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - } ; {Activity date: 08/13/2020; Status: Prior to Final Inspectn; Inspector: GKOZIOL; Comment: Entered by SMONTES1 - SWR_LA ESTANCIA DE TUCSON BLOCK E LOT 20 Q20192530746 SFR - ISSUED WITH PCRWRD CONDITIONS: NO FINAL UNTIL THE PUBLIC SEWER G-2019-032 IS ACCEPTED AND RELEASED BY PCRWRD} |
|
| 03/18/2021 | COT - RSEL - Electrical Final | Passed | {Activity date: 03/18/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - } ; {Activity date: 03/18/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - } |