Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T20CM04641
Permit Details
Apply Date:
07/22/2020
Applicant:
Dana Petty
Description:
SFR MERI296019 T19-M0162
Permit Reviews
Permit Number - T20CM04641
Permit Status: Expired
Permit Description: SFR MERI296019 T19-M0162
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/22/2020 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 08/13/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM04641
Permit Status: Expired
Permit Description: SFR MERI296019 T19-M0162
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
07/22/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Conditions
Permit Number - T20CM04641
Permit Status: Expired
Permit Description: SFR MERI296019 T19-M0162
Date | Description | Comments |
---|---|---|
07/22/2020 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
07/22/2020 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
Outstanding Inspections
Permit Status: Expired
Permit Number: T20CM04641
Permite Description: SFR MERI296019 T19-M0162
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/07/2022 | RSBU - Building Final | N/A | Canceled | Inspection Canceled |
Completed Inspections
Permit Status: Expired
Permit Number: T20CM04641
Permit Description: SFR MERI296019 T19-M0162
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/31/2020 | COT - RSPL - Yard Water Line | Passed | {Activity date: 08/31/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} | |
08/31/2020 | COT - RSPL - Sewer | Passed | {Activity date: 08/31/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} | |
08/31/2020 | COT - RSPL - Rough Soil | Passed | {Activity date: 08/31/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} | |
09/15/2020 | COT - RSBU - Preslab | Passed | {Activity date: 09/15/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by JSCHNEI2 - Approved} | |
09/15/2020 | COT - RSEL - Electrical Underground | Passed | {Activity date: 09/15/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by JSCHNEI2 - Approved} | |
09/15/2020 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 09/15/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by JSCHNEI2 - Approved } |
|
10/15/2020 | COT - RSBU - Roof Nailing | Passed | {Activity date: 10/15/2020; Status: Approved; Inspector: WGALLGHER; Comment: Entered by JSCHNEI2 - Approved} | |
10/15/2020 | COT - RSBU - Exterior Clips/Sheathing | Passed | {Activity date: 10/15/2020; Status: Approved; Inspector: WGALLGHER; Comment: Entered by JSCHNEI2 - Approved} | |
10/20/2020 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 10/20/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by PAHUMAD1 - CODE ECO} | |
10/20/2020 | COT - RSEL - Construction Power | Passed | {Activity date: 10/20/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by PAHUMAD1 - Approved} | |
11/19/2020 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 11/19/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by PAHUMAD1 - } | |
11/19/2020 | COT - LCBU - Framing | Passed | {Activity date: 11/19/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by PAHUMAD1 - } | |
11/19/2020 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 11/19/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by PAHUMAD1 - Approved, Clear Southwest Gas} | |
11/19/2020 | COT - BULD - SWG Clearance | Passed | {Activity date: 11/19/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by PAHUMAD1 - CODE} | |
11/19/2020 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 11/19/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by PAHUMAD1 - Approved, Clear Southwest Gas} | |
12/11/2020 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 12/11/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by PAHUMAD1 - } | |
02/10/2021 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 02/10/2021; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by VLEON1 - APPROVED} ; {Activity date: 09/15/2020; Status: Partial Approval; Inspector: TTREMBULAK; Comment: Entered by JSCHNEI2 - Partial. Ok to pour slab.} | |
02/10/2021 | COT - RSME - Mechanical Final | Passed | {Activity date: 02/10/2021; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by VLEON1 - APPROVED} | |
02/10/2021 | COT - RSEL - Outdoor Lighting | Passed | {Activity date: 02/10/2021; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by VLEON1 - APPROVED} | |
02/10/2021 | COT - RSPL - Plumbing Final | Passed | {Activity date: 02/10/2021; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by VLEON1 - APPROVED} ; {Activity date: 08/13/2020; Status: Prior to Final Inspectn; Inspector: GKOZIOL; Comment: Entered by SMONTES1 - SWR_LA ESTANCIA DE TUCSON BLOCK E LOT 78 Q20192530746 SFR - ISSUED WITH PCRWRD CONDITIONS: NO FINAL UNTIL THE PUBLIC SEWER G-2019-032 IS ACCEPTED AND RELEASED BY PCRWRD} |
|
02/10/2021 | RSME - Mechanical Progress | Passed | {Activity date: 02/10/2021; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by VLEON1 - APPROVED} | |
02/10/2021 | COT - RSEL - Electrical Final | Passed | {Activity date: 02/10/2021; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by VLEON1 - APPROVED} |