Permit: T20CM04622
Permit Details
Status:
Final
Type:
SINGLE FAMILY NEW
Address:
3025 E SAM HUGHES CT
Address NEW:
3025 E SAM HUGHES CT
Apply Date:
07/22/2020
Applicant:
A F STERLING HOME BUILDERS LTD
Description:
SFR AF2193T19 T19-M0069
Contractors:
- A F STERLING HOME BUILDERS LTD
Permit Reviews
Permit Number - T20CM04622
Permit Status: Final
Permit Description: SFR AF2193T19 T19-M0069
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/22/2020 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 07/22/2020 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T20CM04622
Permit Description: SFR AF2193T19 T19-M0069
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/20/2020 | PLUMBING - SEWER HCS CONNECT | TTREMBULAK | Approved | Approved |
| 08/20/2020 | PLUMBING - YARD WTR LINE/TEST | TTREMBULAK | Approved | Approved |
| 08/20/2020 | PLUMBING - ROUGH, SOIL | TTREMBULAK | Approved | Approved |
| 08/25/2020 | ELECTRIC - UNDERGROUND | TTREMBULAK | Approved | Approved |
| 08/25/2020 | BUILDING PRE-SLAB | TTREMBULAK | Approved | Approved |
| 08/25/2020 | EXCAVATION/LAYOUT REBAR & ZON | TTREMBULAK | Approved | Approved |
| 09/15/2020 | ROOF NAILING | ESTEVENS | Approved | Both are approved. |
| 09/15/2020 | EXT METAL CLIPS/EXT SHEATHING | ESTEVENS | Approved | Both are approved. |
| 10/09/2020 | TEP CLEARANCE - AM | BBENEDON | Approved | CODE ECO |
| 10/09/2020 | OUTDOOR LIGHTING FINAL | ESTEVENS | Approved | CODE ECO |
| 10/09/2020 | ELECTRIC - UFER | ESTEVENS | Approved | Both are approved. The TEP clearance code is ECO. |
| 10/09/2020 | ELECTRIC - CONSTRUCTION POWER | ESTEVENS | Approved | Both are approved. The TEP clearance code is ECO. |
| 10/28/2020 | GAS CLEARANCE | ESTEVENS | Approved | CODE |
| 10/28/2020 | FRAMING | ESTEVENS | Approved | All five are approved. Southwest gas clearance is required. |
| 10/28/2020 | RESIDENTIAL INTERMEDIATE | ESTEVENS | Approved | All five are approved. Southwest gas clearance is required. |
| 10/28/2020 | PLUMBING - INTERMEDIATE | ESTEVENS | Approved | All five are approved. Southwest gas clearance is required. |
| 10/28/2020 | PLUMBING - GAS PRESSURE TEST | ESTEVENS | Approved | All five are approved. Southwest gas clearance is required. |
| 10/28/2020 | MECHANICAL - INTERMEDIATE | ESTEVENS | Approved | All five are approved. Southwest gas clearance is required. |
| 11/25/2020 | SHEET ROCK NAILING | ESTEVENS | Approved | Approved. |
| 03/09/2021 | MECHANICAL - FINAL | JBURGE | Approved | APPROVED |
| 03/09/2021 | PLUMBING - FINAL | JBURGE | Approved | APPROVED OK TO SET GAS METER |
| 03/09/2021 | ELECTRIC - FINAL | JBURGE | Approved | APPROVED |
| 03/09/2021 | BUILDING - FINAL | JBURGE | Approved | APPROVED |