Permit: T20CM04620
Permit Details
Apply Date:
07/22/2020
Applicant:
Kimberly York
Description:
SFR KBHO146519 T19-M0156
Permit Reviews
Permit Number - T20CM04620
Permit Status: Expired
Permit Description: SFR KBHO146519 T19-M0156
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/22/2020 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 07/22/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM04620
Permit Status: Expired
Permit Description: SFR KBHO146519 T19-M0156
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
07/22/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Conditions
Permit Number - T20CM04620
Permit Status: Expired
Permit Description: SFR KBHO146519 T19-M0156
Date | Description | Comments |
---|---|---|
11/12/2020 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
Outstanding Inspections
Permit Status: Expired
Permit Number: T20CM04620
Permite Description: SFR KBHO146519 T19-M0156
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/07/2022 | RSBU - Building Final | N/A | Canceled | Inspection Canceled |
Completed Inspections
Permit Status: Expired
Permit Number: T20CM04620
Permit Description: SFR KBHO146519 T19-M0156
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/11/2020 | COT - RSPL - Sewer | Passed | {Activity date: 08/11/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by RSALDAT1 - Approved} | |
08/11/2020 | COT - RSPL - Rough Soil | Passed | {Activity date: 08/11/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by RSALDAT1 - Approved} | |
08/26/2020 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 08/26/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by JSCHNEI2 - Approved} | |
08/26/2020 | COT - RSBU - Preslab | Passed | {Activity date: 08/26/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by JSCHNEI2 - Approved} | |
08/26/2020 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 08/26/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by JSCHNEI2 - Approved} | |
09/15/2020 | COT - RSBU - Roof Nailing | Passed | {Activity date: 09/15/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by JSCHNEI2 - Approved} | |
09/15/2020 | COT - RSBU - Exterior Clips/Sheathing | Passed | {Activity date: 09/15/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by JSCHNEI2 - Approved} | |
09/24/2020 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 09/24/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by JSCHNEI2 - CODE ECO } |
|
09/24/2020 | COT - RSEL - Construction Power | Passed | {Activity date: 09/24/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by JSCHNEI2 - Approved ok for Clearance eco } |
|
10/08/2020 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 10/08/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by JSCHNEI2 - Approved } ; {Activity date: 10/06/2020; Status: Cancelled; Inspector: TTREMBULAK; Comment: Entered by JSCHNEI2 - ** all cancelled by contractor. Not ready ** } |
|
10/08/2020 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 10/08/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by JSCHNEI2 - Approved } ; {Activity date: 10/06/2020; Status: Cancelled; Inspector: TTREMBULAK; Comment: Entered by JSCHNEI2 - ** all cancelled by contractor. Not ready ** } |
|
10/08/2020 | COT - BULD - SWG Clearance | Passed | {Activity date: 10/08/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by JSCHNEI2 - CODE } |
|
10/08/2020 | RSME - Mechanical Progress | Passed | {Activity date: 10/08/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by JSCHNEI2 - Approved } ; {Activity date: 10/06/2020; Status: Cancelled; Inspector: TTREMBULAK; Comment: Entered by JSCHNEI2 - ** all cancelled by contractor. Not ready ** } |
|
10/08/2020 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 10/08/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by JSCHNEI2 - Approved Clearance for SWGAS connect ok. } ; {Activity date: 10/06/2020; Status: Cancelled; Inspector: TTREMBULAK; Comment: Entered by JSCHNEI2 - ** all cancelled by contractor. Not ready ** } |
|
10/26/2020 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 10/26/2020; Status: Approved; Inspector: TTREMVBULAK; Comment: Entered by RSALDAT1 - Approved} ; {Activity date: 10/23/2020; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by PAHUMAD1 - INSPECTION CANCELLED BY CONTRACTOR} | |
03/04/2021 | COT - RSME - Mechanical Final | Passed | {Activity date: 03/04/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - } | |
03/04/2021 | COT - LCBU - Framing | Passed | {Activity date: 03/04/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - } | |
03/04/2021 | COT - RSPL - Yard Water Line | Passed | {Activity date: 03/04/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - } ; {Activity date: 08/11/2020; Status: Partial Approval; Inspector: TTREMBULAK; Comment: Entered by RSALDAT1 - Partial. Ok to backfill. No meter installed.} | |
03/04/2021 | COT - RSEL - Outdoor Lighting | Passed | {Activity date: 03/04/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - } | |
03/04/2021 | COT - RSEL - Electrical Underground | Passed | {Activity date: 03/04/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - } | |
03/04/2021 | COT - RSPL - Plumbing Final | Passed | {Activity date: 03/04/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - } | |
03/04/2021 | COT - RSEL - Electrical Final | Passed | {Activity date: 03/04/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - } |