Permit Details

Status:
Final
Type:
SINGLE FAMILY NEW
Address:
2567 W KIPPY TR
Apply Date:
07/13/2020
Applicant:
D R H TUCSON CONSTRUCTION
Description:
SFR DRHOH30G19 T19-M0138
Contractors:
  • D R H TUCSON CONSTRUCTION

Permit Reviews

Permit Number - T20CM04408
Permit Status: Final
Permit Description: SFR DRHOH30G19 T19-M0138
Start Date Submittal Complete Date Status  
07/13/2020 RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO 07/22/2020 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T20CM04408
Permit Status: Final
Permit Description: SFR DRHOH30G19 T19-M0138
Total Outstanding Activity Conditions - 1
Date Name
07/13/2020 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T20CM04408
Permit Description: SFR DRHOH30G19 T19-M0138
Total Completed Inspections - 25
Date Description Inspector Results Comments
08/07/2020 PLUMBING - ROUGH, SOIL ESTEVENS Approved All three are approved.
08/07/2020 PLUMBING - YARD WTR LINE/TEST ESTEVENS Approved All three are approved.
08/07/2020 PLUMBING - SEWER HCS CONNECT ESTEVENS Approved All three are approved.
09/01/2020 TEP CLEARANCE - PM ESTEVENS Approved CODE ECO
09/01/2020 EXCAVATION/LAYOUT REBAR & ZON ESTEVENS Approved All five are approved. The TEP clearance code is ECO.
09/01/2020 BUILDING PRE-SLAB ESTEVENS Approved All five are approved. The TEP clearance code is ECO.
09/01/2020 ELECTRIC - UFER ESTEVENS Approved All five are approved. The TEP clearance code is ECO.
09/01/2020 ELECTRIC - UNDERGROUND ESTEVENS Approved All five are approved. The TEP clearance code is ECO.
09/01/2020 ELECTRIC - CONSTRUCTION POWER ESTEVENS Approved All five are approved. The TEP clearance code is ECO.
10/26/2020 ROOF NAILING DQUINN Approved
10/26/2020 EXT METAL CLIPS/EXT SHEATHING DQUINN Approved
11/20/2020 GAS CLEARANCE DQUINN Approved CODE
11/20/2020 PLUMBING - GAS PRESSURE TEST DQUINN Approved Clear gas
11/20/2020 RESIDENTIAL INTERMEDIATE DQUINN Approved Clear gas
12/09/2020 MECHANICAL - INTERMEDIATE RBOOHER Approved
12/09/2020 PLUMBING - INTERMEDIATE RBOOHER Approved
12/09/2020 MECHANICAL - INTERMEDIATE RBOOHER Approved
12/09/2020 PLUMBING - INTERMEDIATE RBOOHER Approved
12/09/2020 FRAMING RBOOHER Approved
12/23/2020 SHEET ROCK NAILING DQUINN Approved Ap
02/10/2021 MECHANICAL - FINAL DQUINN Approved APPROVED
02/10/2021 PLUMBING - FINAL DQUINN Approved APPROVED
02/10/2021 OUTDOOR LIGHTING FINAL DQUINN Approved APPROVED
02/10/2021 ELECTRIC - FINAL DQUINN Approved APPROVED
02/14/2021 BUILDING - FINAL BSTEVENS Approved

Documents

File Name Document Type  
FINAL SIC.PDF DOCUMENTS VIEW
HERS FORM.PDF DOCUMENTS VIEW