Permit: T20CM04405
Permit Details
Apply Date:
07/13/2020
Applicant:
D R H TUCSON CONSTRUCTION
Description:
SFR DRHOH35B19 T19-M0140
Contractors:
- D R H TUCSON CONSTRUCTION
Permit Reviews
Permit Number - T20CM04405
Permit Status: Final
Permit Description: SFR DRHOH35B19 T19-M0140
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/13/2020 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 07/22/2020 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T20CM04405
Permit Description: SFR DRHOH35B19 T19-M0140
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/07/2020 | PLUMBING - ROUGH, SOIL | ESTEVENS | Approved | All three are approved. |
08/07/2020 | PLUMBING - YARD WTR LINE/TEST | ESTEVENS | Approved | All three are approved. |
08/07/2020 | PLUMBING - SEWER HCS CONNECT | ESTEVENS | Approved | All three are approved. |
09/01/2020 | TEP CLEARANCE - PM | ESTEVENS | Approved | CODE ECO |
09/01/2020 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVENS | Approved | All five are approved. The TEP clearance code is ECO. |
09/01/2020 | BUILDING PRE-SLAB | ESTEVENS | Approved | All five are approved. The TEP clearance code is ECO. |
09/01/2020 | ELECTRIC - UFER | ESTEVENS | Approved | All five are approved. The TEP clearance code is ECO. |
09/01/2020 | ELECTRIC - UNDERGROUND | ESTEVENS | Approved | All five are approved. The TEP clearance code is ECO. |
09/01/2020 | ELECTRIC - CONSTRUCTION POWER | ESTEVENS | Approved | All five are approved. The TEP clearance code is ECO. |
10/21/2020 | ROOF NAILING | ESTEVENS | Approved | |
10/21/2020 | EXT METAL CLIPS/EXT SHEATHING | ESTEVENS | Approved | |
11/18/2020 | GAS CLEARANCE | DQUINN | Approved | CODE |
11/18/2020 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | Clear gas |
11/18/2020 | RESIDENTIAL INTERMEDIATE | DQUINN | Approved | Clear gas |
12/01/2020 | SHEET ROCK NAILING | DQUINN | Approved | Please add 1045 to permit |
12/01/2020 | PLUMBING - FINAL | DQUINN | Approved | |
01/21/2021 | PLUMBING - INTERMEDIATE | DQUINN | Approved | APPROVED |
01/21/2021 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | APPROVED |
01/21/2021 | MECHANICAL - FINAL | DQUINN | Approved | APPROVED |
01/21/2021 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | APPROVED |
01/21/2021 | ELECTRIC - FINAL | DQUINN | Approved | APPROVED |
01/21/2021 | FRAMING | DQUINN | Approved | APPROVED |
01/25/2021 | BUILDING - FINAL | KEN | Approved | CERT FILED |