Permit: T20CM04381
Permit Details
Apply Date:
07/13/2020
Applicant:
DEAN ALAN ARCHITECTS
Description:
TI: RED BULL DISTRIBUTION
Architects:
- DEAN ALAN ARCHITECTS
Permit Reviews
Permit Number - T20CM04381
Permit Status: L of c
Permit Description: TI: RED BULL DISTRIBUTION
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/15/2020 | 3RD PARTY REVIEW - COMMERCIAL TI | 08/17/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM04381
Permit Status: L of c
Permit Description: TI: RED BULL DISTRIBUTION
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
07/13/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T20CM04381
Permit Description: TI: RED BULL DISTRIBUTION
Total Completed Inspections - 27
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/20/2020 | PLUMBING - ROUGH, SOIL | WGALLAGHER | Approved | Approved |
08/20/2020 | PLUMBING - ROUGH, SOIL | WGALLAGHER | Approved | Approved |
08/26/2020 | FRAMING | ESTEVENS | Approved | All three are approved. |
08/26/2020 | ELECTRIC - INTERMEDIATE | ESTEVENS | Approved | All three are approved. |
08/26/2020 | PLUMBING - PRE SLAB | ESTEVENS | Approved | All three are approved. |
09/02/2020 | MECHANICAL - ABOVE CEILING | ESTEVENS | Approved | All four are approved. |
09/02/2020 | PLUMBING - ABOVE CEILING | ESTEVENS | Approved | All four are approved. |
09/02/2020 | ELECTRIC - ABOVE CEILING | ESTEVENS | Approved | All four are approved. |
09/02/2020 | BUILDING ABOVE CEILING | ESTEVENS | Approved | All four are approved. |
09/11/2020 | SHEET ROCK NAILING | DQUINN | Approved | Ap |
09/11/2020 | MECHANICAL - FINAL | DQUINN | Approved | Ap |
09/11/2020 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | Ap |
09/11/2020 | PLUMBING - INTERMEDIATE | DQUINN | Approved | Ap |
09/11/2020 | ELECTRIC - FINAL | DQUINN | Approved | Ap |
09/11/2020 | ELECTRIC - PROGRESS | DQUINN | Approved | Ap |
09/11/2020 | BUILDING - FINAL | DQUINN | Approved | Ap |
09/11/2020 | BUILDING - PROGRESS | DQUINN | Approved | Ap |
09/11/2020 | FIRE - FINAL | jfordney | Approved | |
09/11/2020 | FIRE SPKLR - FINAL | jfordney | Approved | |
09/11/2020 | FIRE - ALARM FINAL | jfordney | Approved | |
09/11/2020 | RIGHT OF WAY - FINAL | DR | Approved | |
09/11/2020 | NPPO - FINAL | BBENEDON | Approved | Approved |
09/11/2020 | SIGN - FINAL | BBENEDON | Approved | Approved |
09/11/2020 | LANDSCAPE - FINAL | BBENEDON | Approved | Approved |
09/11/2020 | ENGINEERING - FINAL | BBENEDON | Approved | Approved |
09/16/2020 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |
11/17/2020 | PLUMBING - PROGRESS | RSHERRY | Approved |