Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T20CM04019
Permit Details
Status:
Expired
Type:
Residential Building - One or Two Family
Address:
12711 E AMERICAN PEAK DR
Address NEW:
12711 E AMERICAN PEAK DR
Apply Date:
06/26/2020
Applicant:
Description:
SFR LENN3501 T19-M0004
Permit Reviews
Permit Number - T20CM04019
Permit Status: Expired
Permit Description: SFR LENN3501 T19-M0004
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/26/2020 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 07/22/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM04019
Permit Status: Expired
Permit Description: SFR LENN3501 T19-M0004
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/26/2020 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
Conditions
Permit Number - T20CM04019
Permit Status: Expired
Permit Description: SFR LENN3501 T19-M0004
| Date | Description | Comments |
|---|---|---|
| 06/26/2020 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
Completed Inspections
Permit Status: Expired
Permit Number: T20CM04019
Permit Description: SFR LENN3501 T19-M0004
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/31/2020 | COT - RSPL - Yard Water Line | Passed | {Activity date: 07/31/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved} | |
| 07/31/2020 | COT - RSPL - Sewer | Passed | {Activity date: 07/31/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved} | |
| 07/31/2020 | COT - RSPL - Rough Soil | Passed | {Activity date: 07/31/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved} | |
| 08/12/2020 | COT - RSBU - Preslab | Passed | {Activity date: 08/12/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by JSCHNEI2 - Approved} | |
| 08/12/2020 | COT - RSEL - Electrical Underground | Passed | {Activity date: 08/12/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by JSCHNEI2 - Approved} | |
| 08/12/2020 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 08/12/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by JSCHNEI2 - Approved} | |
| 09/10/2020 | COT - RSBU - Roof Nailing | Passed | {Activity date: 09/10/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by JSCHNEI2 - Approved} | |
| 09/10/2020 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | {Activity date: 09/10/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by JSCHNEI2 - Approved} | |
| 09/15/2020 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 09/15/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by RSALDAT1 - Approved} ; {Activity date: 08/12/2020; Status: Partial Approval; Inspector: TTREMBULAK; Comment: Entered by JSCHNEI2 - Partial. Ok to pour slab.} | |
| 09/15/2020 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 09/15/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by RSALDAT1 - CODE ECO} | |
| 09/15/2020 | COT - RSEL - Construction Power | Passed | {Activity date: 09/15/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by RSALDAT1 - Approved Clearance for TEP ECO connect ok.} | |
| 10/05/2020 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 10/05/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by JSCHNEI2 - Approved} | |
| 10/05/2020 | COT - LCBU - Framing | Passed | {Activity date: 10/05/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by JSCHNEI2 - Approved} | |
| 10/05/2020 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 10/05/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by JSCHNEI2 - Approved} | |
| 10/05/2020 | RSME - Mechanical Progress | Passed | {Activity date: 10/05/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by JSCHNEI2 - Approved} | |
| 10/05/2020 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 10/05/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by JSCHNEI2 - Approved ok for clearance} | |
| 10/12/2020 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 10/12/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VFLORES1 - } | |
| 12/08/2020 | COT - BULD - SWG Clearance | Passed | {Activity date: 12/08/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by PAHUMAD1 - CODE} ; {Activity date: 10/05/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by JSCHNEI2 - CODE } |
|
| 12/17/2020 | COT - RSME - Mechanical Final | Passed | {Activity date: 12/17/2020; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - APPROVED} | |
| 12/17/2020 | RSBU - Building Final | Passed | {Activity date: 12/17/2020; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - APPROVED} ; {Activity date: 10/05/2020; Status: Not ready for Inspection; Inspector: WGALLAGHER; Comment: Entered by JSCHNEI2 - Not ready} | |
| 12/17/2020 | COT - RSEL - Outdoor Lighting | Passed | {Activity date: 12/17/2020; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - APPROVED} | |
| 12/17/2020 | COT - RSPL - Plumbing Final | Passed | {Activity date: 12/17/2020; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - APPROVED} ; {Activity date: 12/08/2020; Status: Not ready for Inspection; Inspector: WGALLAGHER; Comment: Entered by PAHUMAD1 - Not ready} | |
| 12/17/2020 | COT - RSEL - Electrical Final | Passed | {Activity date: 12/17/2020; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - APPROVED} |