Permit: T20CM03956
Permit Details
Apply Date:
06/24/2020
Applicant:
Albert LeCocq
Description:
NEW APARTMENT BLDG
Permit Reviews
Permit Number - T20CM03956
Permit Status: Complete
Permit Description: NEW APARTMENT BLDG
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/01/2020 | PLANS OK TO SUBMIT - COMM | 07/08/2020 | COMPLETED |
07/08/2020 | 3RD PARTY REVIEW - COMMERCIAL | 09/30/2020 | COMPLETED |
12/01/2020 | 3RD PARTY REVIEW - REVISION/OTHER | 03/01/2021 | COMPLETED |
06/13/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/17/2024 | APPROVED |
Conditions
Permit Number - T20CM03956
Permit Status: Complete
Permit Description: NEW APARTMENT BLDG
Date | Description | Comments |
---|---|---|
03/15/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
03/15/2024 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
03/15/2024 | Plan review applications expire 180 days from date of submittal unless the permit has been issued. Permits expire 180 days after issuance or last approved inspection. | |
03/15/2024 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
03/15/2024 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
03/15/2024 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T20CM03956
Permite Description: NEW APARTMENT BLDG
Total Outstanding Inspections - 3
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/04/2022 | PDSD Site/Engineering Division - Landscaping | N/A | Canceled | Inspection Canceled |
11/04/2022 | COT - FCON - Alarm - Final | N/A | Canceled | Inspection Canceled |
11/04/2022 | COT - FCON - Sprinkler - Final | N/A | Canceled | Inspection Canceled |
Completed Inspections
Permit Status: Complete
Permit Number: T20CM03956
Permit Description: NEW APARTMENT BLDG
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/10/2021 | COT - LCBU - Excavation/Rebar/Zoning | Passed | {Activity date: 03/10/2021; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VLEON1 - Approved. From the outside of building to the main 6 inch private sewer. } |
|
03/10/2021 | COT - LCEL - Temporary Service | Passed | {Activity date: 03/10/2021; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VLEON1 - Approved. Meters for the following units. 61 through 76 plus the house meter.} | |
03/10/2021 | COT - LCPL - Yard Water Line | Passed | {Activity date: 03/10/2021; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VLEON1 - Approved. Portable water for unit 61 through 67.} | |
04/12/2021 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 04/12/2021; Status: Approved; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - CODE TMPP/UNITS 61-76 AND HOUSE METER} | |
07/02/2021 | COT - LCBU - Framing | Passed | {Activity date: 07/02/2021; Status: Approved; Inspector: RELEFANTE; Comment: Entered by VLEON1 - } | |
07/02/2021 | COT - LCBU - Roof Nailing | Passed | {Activity date: 07/02/2021; Status: Approved; Inspector: RELEFANTE; Comment: Entered by VLEON1 - } | |
10/14/2021 | COT - LCBU - Building Final | Passed | {Activity date: 10/14/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved, Building #5, units 61-76} | |
10/14/2021 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 10/14/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - } ; {Activity date: 10/11/2021; Status: Cancelled; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - cancelled by Contractor, will reschedule} | |
10/14/2021 | COT - LCME - Mechanical Final | Passed | {Activity date: 10/14/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved} | |
10/14/2021 | COT - LCEL - Outdoor Lighting | Passed | {Activity date: 10/14/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved} | |
10/14/2021 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 10/14/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - } ; {Activity date: 10/11/2021; Status: Cancelled; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - cancelled by Contractor, will reschedule} | |
10/14/2021 | COT - LCEL - Electrical Final | Passed | {Activity date: 10/14/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - } | |
10/14/2021 | COT - LCPL - Rough Soil | Passed | {Activity date: 10/14/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - } | |
10/14/2021 | COT - LCME - Mechanical Intermediate | Passed | {Activity date: 10/14/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - } ; {Activity date: 10/11/2021; Status: Cancelled; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - cancelled by Contractor, will reschedule} | |
10/14/2021 | COT - LCPL - Plumbing Final | Passed | {Activity date: 10/14/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved} | |
10/14/2021 | COT - LCEL - Grounding/Bonding | Passed | {Activity date: 10/14/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - } ; {Activity date: 10/12/2021; Status: Not ready for Inspection; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - NR, pending Electrical Final 02/05/2021 1035 TGAUSP FRAMING Approved is Approved 02/05/2021 2035 TGAUSP ELECTRIC - INTERMEDIATE Approved is Approved 02/03/2021 3035 TGAUSP PLUMBING - INTERMEDIATE Approved 1st floor apartments #5, #6, #7, #8 are Approved Water and DWV not on test in 2nd floor apartments #9, #10, #11, #12, #13, #14, #15, #16 Not Ready (NR) 2/3/2021 4035 MECHANICAL - INTERMEDIATE TGAUSP Partial Approval 3/10/2021 3057 SITE - SEWER ESTEVENS Cancelled} |
|
12/07/2023 | TRSP - ROW - Final/Close-Out | Passed | ||
12/06/2023 | ENGR Engineering Final | Passed | ||
12/06/2023 | COT - FCON - Fire - Final | Passed | ||
12/06/2023 | COT - BULD - SWG Clearance | Passed | No clearance required. | |
12/06/2023 | BULD - Electrical Clearance | Passed | No clearance required |