Permit Details

Status:
Expired
Type:
Commercial Building
Address NEW:
2522 E FORT LOWELL RD
Apply Date:
06/23/2020
Applicant:
Vince Catalano
Description:
TI: INTERIOR REMODEL GALLERY OF FOOD

Permit Reviews

Permit Number - T20CM03898
Permit Status: Expired
Permit Description: TI: INTERIOR REMODEL GALLERY OF FOOD
Start Date Submittal Complete Date Status  
06/23/2020 COMMERCIAL - TI 07/09/2020 COMPLETED Review Details
07/09/2020 RESUBMITTAL 07/17/2020 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T20CM03898
Permit Status: Expired
Permit Description: TI: INTERIOR REMODEL GALLERY OF FOOD
Total Outstanding Activity Conditions - 1
Date Name
06/23/2020 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Outstanding Inspections

Permit Status: Expired
Permit Number: T20CM03898
Permite Description: TI: INTERIOR REMODEL GALLERY OF FOOD
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
11/04/2022 COT - ENGR - Site - Assurance Release N/A Canceled Inspection Canceled
11/07/2022 COT - FCON - Fire - Final N/A Canceled Inspection Canceled

Completed Inspections

Permit Status: Expired
Permit Number: T20CM03898
Permit Description: TI: INTERIOR REMODEL GALLERY OF FOOD
Total Completed Inspections - 13
Date Description Inspector Results Comments
07/30/2020 COT - LCPL - Rough Soil Passed {Activity date: 07/30/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by JSCHNEI2 - Approved}
08/19/2020 COT - LCBU - Preslab Passed {Activity date: 08/19/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by JSCHNEI2 - Approved}
08/25/2020 COT - LCPL - Plumbing Intermediate Passed {Activity date: 08/25/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - Approved.} ; {Activity date: 08/19/2020; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by JSCHNEI2 - Partial approval for pre slab} ; {Activity date: 08/14/2020; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by JSCHNEI2 - Partial approval ok to cover waste line inside

} ; {Activity date: 08/06/2020; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Partial approval for grease trap placement and for sewer line from trap to existing
Need leak check on trap}
09/01/2020 COT - LCPL - Gas Pressure Test Passed {Activity date: 09/01/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - Both are approved. Southwest gas clearance is Required.} ; {Activity date: 07/30/2020; Status: Partial Approval; Inspector: TTREMBULAK; Comment: Entered by JSCHNEI2 - Partial. Outside line ok to backfill.}
09/01/2020 COT - LCBU - Framing Passed {Activity date: 09/01/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - Both are approved. Southwest gas clearance is Required.} ; {Activity date: 08/07/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - Partial. Gas pressure test is required before wall can be dry-walled.

}
09/01/2020 COT - BULD - SWG Clearance Passed {Activity date: 09/01/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - CODE}
09/04/2020 COT - LCPL - Plumbing Final Passed {Activity date: 09/04/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by JSCHNEI2 - Approved.} ; {Activity date: 06/23/2020; Status: Prior to Final Inspectn; Inspector: RSHERRY; Comment: Entered by RSHERRY1 - WATER DISINFECTION REPORT REQUIRED}
09/10/2020 COT - LCBU - Building Above Ceiling Passed {Activity date: 09/10/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by JSCHNEI2 - Approved} ; {Activity date: 08/10/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by JSCHNEI2 - Partial. Ok, missing cut out for kitchen hood area.}
09/10/2020 COT - LCME - Kitchen Hood Passed {Activity date: 09/10/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by JSCHNEI2 - Approved}
09/10/2020 COT - LCME - Mechanical Intermediate Passed {Activity date: 09/10/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by JSCHNEI2 - Approved} ; {Activity date: 08/20/2020; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by JSCHNEI2 - Partial approval for hood duct smoke leak test and insulation wrap inspection}
09/17/2020 COT - LCME - Mechanical Final Passed {Activity date: 09/17/2020; Status: Approved; Inspector: DQUINN; Comment: Entered by RSALDAT1 - Ap} ; {Activity date: 06/23/2020; Status: Prior to Final Inspectn; Inspector: RSHERRY; Comment: Entered by RSHERRY1 - AIR BALANCE REPORT REQUIRED}
09/17/2020 ENGR Engineering Final Passed {Activity date: 09/17/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Approved.} ; {Activity date: 08/10/2020; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Not ready. Christine Is looking for an intermediate building inspection. They have one roll off dumpster on site. They are replacing hood. She will reschedule for final inspection on the project has been completed

}
09/22/2020 COT - LCBU - Building Final Passed {Activity date: 09/22/2020; Status: Approved; Inspector: DQUINN; Comment: Entered by JSCHNEI2 - Ap

Ok for c of o}