Permit: T20CM03780
Permit Details
Apply Date:
06/17/2020
Applicant:
MATTAMY ARIZONA CONSTRUCTION L L C ** APA **
Description:
SFR F40J19 T19-M0035
Contractors:
- MATTAMY ARIZONA CONSTRUCTION L L C ** APA **
Permit Reviews
Permit Number - T20CM03780
Permit Status: Final
Permit Description: SFR F40J19 T19-M0035
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/17/2020 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 06/22/2020 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T20CM03780
Permit Description: SFR F40J19 T19-M0035
Total Completed Inspections - 25
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/29/2020 | ELECTRIC - UFER | TTREMBULAK | Approved | Partial. Ok to pour slab. |
07/29/2020 | PLUMBING - SEWER HCS CONNECT | TTREMBULAK | Approved | Approved |
07/29/2020 | PLUMBING - ROUGH, SOIL | TTREMBULAK | Approved | Approved |
07/29/2020 | ELECTRIC - UNDERGROUND | TTREMBULAK | Approved | Approved |
07/29/2020 | EXCAVATION/LAYOUT REBAR & ZON | TTREMBULAK | Approved | Approved |
09/14/2020 | FRAMING | WGALLAGHER | Approved | Approved |
09/14/2020 | ROOF NAILING | WGALLAGHER | Approved | Approved |
09/14/2020 | EXT METAL CLIPS/EXT SHEATHING | WGALLAGHER | Approved | Approved |
09/14/2020 | BUILDING PRE-SLAB | WGALLAGHER | Approved | Approved |
11/03/2020 | MECHANICAL - INTERMEDIATE | WGALLAGHER | Approved | Approved |
11/03/2020 | PLUMBING - GAS PRESSURE TEST | WGALLAGHER | Approved | Approved |
11/03/2020 | ELECTRIC - CONSTRUCTION POWER | WGALLAGHER | Approved | Not ready |
11/03/2020 | RESIDENTIAL INTERMEDIATE | WGALLAGHER | Approved | Approved |
12/02/2020 | SHEET ROCK NAILING | WGALLAGHER | Approved | |
01/06/2021 | TEP CLEARANCE - PM | RCHANDLER | Approved | CODE TMPP |
01/06/2021 | ELECTRIC - TEMPORARY SERVICE | RCHANDLER | Approved | AP. TMPP clearance for TEP. |
01/28/2021 | MECHANICAL - FINAL | RCHANDLER | Approved | APPROVED |
01/28/2021 | PLUMBING - FINAL | RCHANDLER | Approved | APPROVED |
01/29/2021 | ELECTRIC - FINAL | RCHANDLER | Approved | DENIED CORRECTION NOT COMPLETED |
02/02/2021 | PLUMBING - YARD WTR LINE/TEST | RCHANDLER | Approved | APPROVED |
02/02/2021 | OUTDOOR LIGHTING FINAL | RCHANDLER | Approved | APPROVED |
02/02/2021 | BUILDING - FINAL | RCHANDLER | Approved | APPROVED |
02/09/2021 | FIRE SPKLR - OH PIPING & HYDRO | BSTEVENS | Approved | ALL FIRE SPRINKLER INSPECTIONS WERE DONE UNDER T20FC00631 |
02/09/2021 | FIRE SPKLR - UG PIPING FLUSH | BSTEVENS | Approved | ALL FIRE SPRINKLER INSPECTIONS WERE DONE UNDER T20FC00631 |
02/09/2021 | FIRE SPKLR - UG, PIPING, HYDRO | BSTEVENS | Approved | ALL FIRE SPRINKLER INSPECTIONS WERE DONE UNDER T20FC00631 |