Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T20CM03774
Permit Details
Apply Date:
06/17/2020
Applicant:
D R H TUCSON CONSTRUCTION
Description:
SFR DRHOX30A19 T19-M0163
Contractors:
- D R H TUCSON CONSTRUCTION
Permit Reviews
Permit Number - T20CM03774
Permit Status: Final
Permit Description: SFR DRHOX30A19 T19-M0163
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/17/2020 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 07/08/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM03774
Permit Status: Final
Permit Description: SFR DRHOX30A19 T19-M0163
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
06/17/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T20CM03774
Permit Description: SFR DRHOX30A19 T19-M0163
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/15/2020 | PLUMBING - SEWER HCS CONNECT | TTREMBULAK | Approved | Approved(including backwater valve). |
07/15/2020 | PLUMBING - ROUGH, SOIL | TTREMBULAK | Approved | Approved |
07/29/2020 | ELECTRIC - UNDERGROUND | DMUNIZ | Approved | Approved |
07/29/2020 | ELECTRIC - UFER | DMUNIZ | Approved | Approved |
07/29/2020 | BUILDING PRE-SLAB | DMUNIZ | Approved | Approved |
07/29/2020 | EXCAVATION/LAYOUT REBAR & ZON | DMUNIZ | Approved | Approved |
08/14/2020 | ROOF NAILING | DMUNIZ | Approved | Approved |
08/14/2020 | EXT METAL CLIPS/EXT SHEATHING | DMUNIZ | Approved | Approved |
08/28/2020 | GAS CLEARANCE | DMUNIZ | Approved | CODE |
08/28/2020 | TEP CLEARANCE - PM | DMUNIZ | Approved | CODE ECO |
08/28/2020 | ELECTRIC - CONSTRUCTION POWER | DMUNIZ | Approved | Approved clear TEP ECO |
08/28/2020 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | Approved |
08/28/2020 | PLUMBING - GAS PRESSURE TEST | DMUNIZ | Approved | Approved clear Southwest Gas |
08/28/2020 | PLUMBING - YARD WTR LINE/TEST | DMUNIZ | Approved | Approved |
08/28/2020 | PLUMBING - INTERMEDIATE | DMUNIZ | Approved | Approved |
08/28/2020 | FRAMING | DMUNIZ | Approved | Approved |
08/28/2020 | RESIDENTIAL INTERMEDIATE | DMUNIZ | Approved | Approved |
09/10/2020 | SHEET ROCK NAILING | DMUNIZ | Approved | Approved |
10/27/2020 | MECHANICAL - FINAL | DMUNIZ | Approved | |
10/27/2020 | PLUMBING - FINAL | DMUNIZ | Approved | |
10/27/2020 | OUTDOOR LIGHTING FINAL | DMUNIZ | Approved | |
10/27/2020 | ELECTRIC - FINAL | DMUNIZ | Approved | |
10/27/2020 | BUILDING - FINAL | DMUNIZ | Approved |