Permit Details

Status:
C of o
Type:
COMMERCIAL ALTERATION
Apply Date:
06/09/2020
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
TI: RETAIL
Architects:
  • FRANKS, MICHAEL WILLIAM

Permit Reviews

Permit Number - T20CM03529
Permit Status: C of o
Permit Description: TI: RETAIL
Start Date Submittal Complete Date Status  
06/09/2020 PLANS OK TO SUBMIT - COMM 07/28/2020 COMPLETED Review Details
07/21/2020 3RD PARTY REVIEW - COMMERCIAL TI 08/04/2020 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T20CM03529
Permit Status: C of o
Permit Description: TI: RETAIL
Total Outstanding Activity Conditions - 1
Date Name
06/09/2020 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T20CM03529
Permit Description: TI: RETAIL
Total Completed Inspections - 33
Date Description Inspector Results Comments
08/19/2020 PLUMBING - ROUGH, SOIL DMUNIZ Approved Approved
08/21/2020 PLUMBING - PRE SLAB DUMINIZ Approved Approved
08/26/2020 EXCAVATION/LAYOUT REBAR & ZON DMUNIZ Approved Approved
09/08/2020 SHEET ROCK NAILING DMUNIZ Approved Approved
09/17/2020 PLUMBING - INTERMEDIATE DMUNIZ Approved Approved
09/17/2020 FRAMING DMUNIZ Approved Approved
09/24/2020 GAS CLEARANCE DMUNIZ Approved CODE
09/24/2020 PLUMBING - GAS PRESSURE TEST DMUNIZ Approved Approved, Clear Southwest Gas
10/28/2020 ELECTRIC - UNDERGROUND DMUNIZ Approved Approved, branch circuit and low voltage conduits installed and ok to proceed.
11/23/2020 MECHANICAL - ABOVE CEILING DMUNIZ Approved
11/23/2020 PLUMBING - ABOVE CEILING DMUNIZ Approved
11/23/2020 ELECTRIC - ABOVE CEILING DMUNIZ Approved
11/23/2020 BUILDING ABOVE CEILING DMUNIZ Approved
12/09/2020 NPPO - FINAL BBENEDON Approved Not applicable
12/09/2020 LANDSCAPE - FINAL BBENEDON Approved Not applicable
12/09/2020 RIGHT OF WAY - FINAL Bravin Approved No issues
12/16/2020 PLUMBING - FINAL RBOOHER Approved Approved
12/28/2020 ELECTRIC - INTERMEDIATE RBOOHER Approved 2090
12/28/2020 ELECTRIC - FINAL RBOOHER Approved AP Approved..
12/29/2020 MECHANICAL - PROGRESS DQUINN Approved 4090
12/29/2020 MECHANICAL - FINAL DQUINN Approved 1090
12/29/2020 BUILDING - PROGRESS DQUINN Approved 1090
12/29/2020 MECHANICAL - INTERMEDIATE DQUINN Approved Ap
12/29/2020 ELECTRIC - PROGRESS DQUINN Approved Ap
12/29/2020 PLUMBING - GAS RECONNECT DQUINN Approved Ap
12/29/2020 PLUMBING - PROGRESS DQUINN Approved Ap
12/29/2020 FIRE - FINAL CBASALDUA Approved 1. Ok for TCO for stocking.
2. Sprinklers are monitored by existing building owner.
12/29/2020 BUILDING - FINAL DQUINN Approved PARTIAL, After fire is Ap, Ap 1090, close permit, and issue c of o or letter of completion.
12/29/2020 PLUMBING - GAS PRESS TEST FNL DQUINN Approved APPROVED
01/14/2021 SIGN - FINAL MHERNANDEZ Approved APPROVED
01/14/2021 ENGINEERING - FINAL MHERNANDEZ Approved APPROVED
01/14/2021 SIGN - FINAL MHERNANDEZ Approved CONTINUED
01/14/2021 ENGINEERING - FINAL MHERNANDEZ Approved CONTINUED