Permit: T20CM03529
Permit Details
Apply Date:
06/09/2020
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
TI: RETAIL
Architects:
- FRANKS, MICHAEL WILLIAM
Permit Reviews
Permit Number - T20CM03529
Permit Status: C of o
Permit Description: TI: RETAIL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/09/2020 | PLANS OK TO SUBMIT - COMM | 07/28/2020 | COMPLETED |
07/21/2020 | 3RD PARTY REVIEW - COMMERCIAL TI | 08/04/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM03529
Permit Status: C of o
Permit Description: TI: RETAIL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
06/09/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T20CM03529
Permit Description: TI: RETAIL
Total Completed Inspections - 33
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/19/2020 | PLUMBING - ROUGH, SOIL | DMUNIZ | Approved | Approved |
08/21/2020 | PLUMBING - PRE SLAB | DUMINIZ | Approved | Approved |
08/26/2020 | EXCAVATION/LAYOUT REBAR & ZON | DMUNIZ | Approved | Approved |
09/08/2020 | SHEET ROCK NAILING | DMUNIZ | Approved | Approved |
09/17/2020 | PLUMBING - INTERMEDIATE | DMUNIZ | Approved | Approved |
09/17/2020 | FRAMING | DMUNIZ | Approved | Approved |
09/24/2020 | GAS CLEARANCE | DMUNIZ | Approved | CODE |
09/24/2020 | PLUMBING - GAS PRESSURE TEST | DMUNIZ | Approved | Approved, Clear Southwest Gas |
10/28/2020 | ELECTRIC - UNDERGROUND | DMUNIZ | Approved | Approved, branch circuit and low voltage conduits installed and ok to proceed. |
11/23/2020 | MECHANICAL - ABOVE CEILING | DMUNIZ | Approved | |
11/23/2020 | PLUMBING - ABOVE CEILING | DMUNIZ | Approved | |
11/23/2020 | ELECTRIC - ABOVE CEILING | DMUNIZ | Approved | |
11/23/2020 | BUILDING ABOVE CEILING | DMUNIZ | Approved | |
12/09/2020 | NPPO - FINAL | BBENEDON | Approved | Not applicable |
12/09/2020 | LANDSCAPE - FINAL | BBENEDON | Approved | Not applicable |
12/09/2020 | RIGHT OF WAY - FINAL | Bravin | Approved | No issues |
12/16/2020 | PLUMBING - FINAL | RBOOHER | Approved | Approved |
12/28/2020 | ELECTRIC - INTERMEDIATE | RBOOHER | Approved | 2090 |
12/28/2020 | ELECTRIC - FINAL | RBOOHER | Approved | AP Approved.. |
12/29/2020 | MECHANICAL - PROGRESS | DQUINN | Approved | 4090 |
12/29/2020 | MECHANICAL - FINAL | DQUINN | Approved | 1090 |
12/29/2020 | BUILDING - PROGRESS | DQUINN | Approved | 1090 |
12/29/2020 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | Ap |
12/29/2020 | ELECTRIC - PROGRESS | DQUINN | Approved | Ap |
12/29/2020 | PLUMBING - GAS RECONNECT | DQUINN | Approved | Ap |
12/29/2020 | PLUMBING - PROGRESS | DQUINN | Approved | Ap |
12/29/2020 | FIRE - FINAL | CBASALDUA | Approved | 1. Ok for TCO for stocking. 2. Sprinklers are monitored by existing building owner. |
12/29/2020 | BUILDING - FINAL | DQUINN | Approved | PARTIAL, After fire is Ap, Ap 1090, close permit, and issue c of o or letter of completion. |
12/29/2020 | PLUMBING - GAS PRESS TEST FNL | DQUINN | Approved | APPROVED |
01/14/2021 | SIGN - FINAL | MHERNANDEZ | Approved | APPROVED |
01/14/2021 | ENGINEERING - FINAL | MHERNANDEZ | Approved | APPROVED |
01/14/2021 | SIGN - FINAL | MHERNANDEZ | Approved | CONTINUED |
01/14/2021 | ENGINEERING - FINAL | MHERNANDEZ | Approved | CONTINUED |