Permit: T20CM03416
Permit Details
Apply Date:
06/04/2020
Applicant:
MEMO DURAZO
Description:
NEW SFR
Permit Reviews
Permit Number - T20CM03416
Permit Status: Final
Permit Description: NEW SFR
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/04/2020 | PLANS OK TO SUBMIT - RES | 06/18/2020 | COMPLETED |
06/18/2020 | RESUBMITTAL | 07/01/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM03416
Permit Status: Final
Permit Description: NEW SFR
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
06/04/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T20CM03416
Permit Description: NEW SFR
Total Completed Inspections - 19
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/18/2020 | PLUMBING - ROUGH, SOIL | ESTEVENS | Approved | |
11/24/2020 | ELECTRIC - UFER | JBURGE | Approved | |
11/24/2020 | BUILDING PRE-SLAB | JBURGE | Approved | |
11/24/2020 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | Approved. Ok to place concrete in progress areas |
12/03/2020 | ROOF NAILING | ESTEVENS | Approved | |
12/03/2020 | EXT METAL CLIPS/EXT SHEATHING | ESTEVENS | Approved | |
01/22/2021 | TEP CLEARANCE - AM | DQUINN | Approved | CODE ECO/UNIT #2 |
01/22/2021 | ELECTRIC - CONSTRUCTION POWER | DQUINN | Approved | APPROVED |
01/22/2021 | PLUMBING - INTERMEDIATE | DQUINN | Approved | APPROVED |
01/26/2021 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | APPROVED |
01/26/2021 | RESIDENTIAL INTERMEDIATE | DQUINN | Approved | APPROVED |
01/26/2021 | FRAMING | DQUINN | Approved | APPROVED |
03/12/2021 | SITE - SEWER | TGAUSP | Approved | APPROVED OK TO BACK FILL |
03/12/2021 | PLUMBING - YARD WTR LINE/TEST | TGAUSP | Approved | APPROVED AND CONNECTED TO SEPTIC TANK |
04/06/2021 | MECHANICAL - FINAL | DQUINN | Approved | |
04/06/2021 | PLUMBING - FINAL | DQUINN | Approved | |
04/06/2021 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | |
04/06/2021 | ELECTRIC - FINAL | DQUINN | Approved | |
04/06/2021 | BUILDING - FINAL | DQUINN | Approved |