Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
06/04/2020
Applicant:
Gregory Moore
Description:
NEW MULTI FAMILY

Permit Reviews

Permit Number - T20CM03404
Permit Status: Complete
Permit Description: NEW MULTI FAMILY
Start Date Submittal Complete Date Status  
06/04/2020 PLANS OK TO SUBMIT - COMM 07/20/2020 COMPLETED Review Details
07/24/2020 COMMERCIAL - NEW 09/14/2020 COMPLETED Review Details
11/13/2020 RESUBMITTAL 12/15/2020 COMPLETED Review Details
12/22/2020 RESUBMITTAL 01/26/2021 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T20CM03404
Permit Status: Complete
Permit Description: NEW MULTI FAMILY
Total Outstanding Activity Conditions - 1
Date Name
06/04/2020 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Outstanding Inspections

Permit Status: Complete
Permit Number: T20CM03404
Permite Description: NEW MULTI FAMILY
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
09/24/2021 COT - LCEL - Electrical Underground N/A Canceled {Activity date: 09/24/2021; Status: Not Applicable; Inspector: TGAUSP; Comment: Entered by VVERA1 - NA under slab}
11/04/2022 COT - LCBU - CofO N/A Canceled Inspection Canceled

Completed Inspections

Permit Status: Complete
Permit Number: T20CM03404
Permit Description: NEW MULTI FAMILY
Total Completed Inspections - 33
Date Description Inspector Results Comments
09/15/2021 COT - LCPL - Rough Soil Passed {Activity date: 09/15/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - - Approved, remaining private HCS to units 1101, 1102, 1103, 1104, 1105. Okay to backfill} ; {Activity date: 09/08/2021; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by VVERA1 - Partial, private HCS to Bldg. #1 units 1106,1107,1108,1109,1110}
09/15/2021 COT - LCPL - Backwater Valve Passed {Activity date: 09/15/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved, units 1101,1102,1103,1104}
09/24/2021 COT - LCBU - Excavation/Rebar/Zoning Passed {Activity date: 09/24/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved}
09/24/2021 COT - LCBU - Preslab Passed {Activity date: 09/24/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved}
09/24/2021 COT - LCEL - Grounding/Bonding Passed {Activity date: 09/24/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved}
12/20/2021 COT - LCBU - Exterior Clips/Sheathing Passed {Activity date: 12/20/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved} ; {Activity date: 12/07/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, Sheathing At SW3 locations for exterior fir outs ok to proceed. Install anchor bolts where required.}
12/20/2021 COT - LCBU - Roof Nailing Passed {Activity date: 12/20/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved , okay to dry in} ; {Activity date: 12/07/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, FRTW ROOF DECK and nailing for second floor approved}
03/17/2022 COT - LCPL - Yard Water Line Passed {Activity date: 03/17/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved}
04/15/2022 COT - LCBU - Building Above Ceiling Passed {Activity date: 04/15/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 04/14/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - partial, 1101-1105 ok to proceed}
04/15/2022 COT - LCEL - Electrical Intermediate Passed {Activity date: 04/15/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 04/14/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - partial, 1101-1105 ok to proceed}
04/15/2022 COT - LCBU - Framing Passed {Activity date: 04/15/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 04/14/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - partial, 1101-1105 ok to proceed}
04/15/2022 COT - LCME - Mechanical Above Ceiling Passed {Activity date: 04/15/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 04/14/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - partial, 1101-1105 ok to proceed}
04/15/2022 COT - LCBU - Firewall/Fire Barrier/Firestop Passed {Activity date: 04/15/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 04/14/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - partial, 1101-1105 ok to proceed} ; {Activity date: 12/07/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, 1” FIRE RATED SHAFT LINER installed between demising walls, install clips where required. FRTW roof deck installed.}
04/15/2022 COT - LCPL - Plumbing Intermediate Passed {Activity date: 04/15/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 04/14/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - partial, 1101-1105 ok to proceed}
04/15/2022 COT - LCPL - Plumbing Above Ceiling Passed {Activity date: 04/15/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved}
04/15/2022 COT - LCBU - Sustainability Passed {Activity date: 04/15/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 04/14/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - partial, 1101-1105 ok to proceed}
04/15/2022 COT - LCEL - Electrical Above Ceiling Passed {Activity date: 04/15/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 04/14/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - partial, 1101-1105 ok to proceed}
04/15/2022 COT - LCME - Mechanical Intermediate Passed {Activity date: 04/15/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 04/14/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - partial, 1101-1105 ok to proceed}
04/21/2022 COT - HCBU - Exterior Clips/Sheathing Passed {Activity date: 04/21/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - APPROVED}
05/06/2022 PDSD Building Division - TEP PM Clearance Passed {Activity date: 05/06/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - CODE ECO FOR UNITS 1101,1102,1103,1104,1105,1106,1107,1108,1109,1110} ; {Activity date: 05/25/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - CODE ECO/BLDG #1}
05/06/2022 COT - LCEL - Construction Power Passed {Activity date: 05/06/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved CLEAR TEP ECO for following units 1101,1102,1103,1104,1105,1106,1107,1108,1109,1110

} ; {Activity date: 05/25/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - } ; {Activity date: 05/21/2021; Status: Not ready for Inspection; Inspector: TGAUSP; Comment: Entered by VLEON1 - NOT READY MISSING GROUNDS}
09/06/2022 COT - FCON - Fire - Final Passed {Activity date: 09/06/2022; Status: Approved; Inspector: CBASALDUA; Comment: Entered by CBASALD1 - }
09/12/2022 COT - LCEL - Electrical Progress Passed {Activity date: 09/12/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP 2090}
09/12/2022 COT - LCPL - Plumbing Progress Passed {Activity date: 09/12/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP 3090}
09/12/2022 COT - LCME - Mechanical Final Passed {Activity date: 09/12/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
09/12/2022 COT - LCME - Mechanical Progress Passed {Activity date: 09/12/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP 4090}
09/12/2022 COT - LCEL - Outdoor Lighting Passed {Activity date: 09/12/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
09/12/2022 COT - LCEL - Electrical Final Passed {Activity date: 09/12/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
09/12/2022 COT - LCPL - Sewer Passed {Activity date: 09/12/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP 3090} ; {Activity date: 03/17/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Partial, Interconnection from manholes and HCS stubs from main ok to backfill.} ; {Activity date: 03/10/2021; Status: Not ready for Inspection; Inspector: TGAUSP; Comment: Entered by VLEON1 - }
09/12/2022 COT - LCPL - Plumbing Final Passed {Activity date: 09/12/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP RECD WWR P21WX00935} ; {Activity date: 03/12/2021; Status: Prior to Final Inspectn; Inspector: JGARCIA; Comment: Entered by KROBLES1 - NEED WW RECEIPT}
09/14/2022 COT - LCBU - Building Final Passed {Activity date: 09/14/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - Approved} ; {Activity date: 09/12/2022; Status: Denied; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - DE
Maintain 1 1/2" min between hand rail and wall or any protrusions.}
09/14/2022 COT - LCBU - Building Progress Passed {Activity date: 09/14/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - 1090.Approved}
09/14/2022 COT - HCBU - Interior Shear Bracing Passed {Activity date: 09/14/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - 1090.Approved} ; {Activity date: 05/16/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by VVERA1 - Partial for building 1, units 1105,1106,1107,1108, 1109,1110} ; {Activity date: 05/10/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial for building 1, units 1101,1102,1103,1104}

Documents

File Name Document Type  
TCO T20CM03404 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
TCO T20CM03404.PDF DOCUMENTS VIEW
TCO T20CM03404.PDF DOCUMENTS VIEW
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
AFFORDABLE HOUSING WAIVER AUTH BLDG 1.PDF DOCUMENTS VIEW
SOILS REPORT.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
PETITION OF APPEAL TO THE FIRE CODE OFFICIAL.PDF DOCUMENTS VIEW
SPECIAL INSPECTION CERT.PDF DOCUMENTS VIEW
PLAN SET.PDF CONSTRPLANS VIEW