Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
06/04/2020
Applicant:
RICK BRIGHT
Description:
NEW MULTI FAMILY

Permit Reviews

Permit Number - T20CM03400
Permit Status: Complete
Permit Description: NEW MULTI FAMILY
Start Date Submittal Complete Date Status  
06/04/2020 PLANS OK TO SUBMIT - COMM 07/24/2020 COMPLETED Review Details
07/24/2020 COMMERCIAL - NEW 09/14/2020 COMPLETED Review Details
11/06/2020 RESUBMITTAL 12/14/2020 COMPLETED Review Details
11/13/2020 RESUBMITTAL 12/08/2020 COMPLETED Review Details

Conditions

Permit Number - T20CM03400
Permit Status: Complete
Permit Description: NEW MULTI FAMILY
Date Description Comments
06/04/2020 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Outstanding Inspections

Permit Status: Complete
Permit Number: T20CM03400
Permite Description: NEW MULTI FAMILY
Total Outstanding Inspections - 4
Last Inspection Date Description Inspector Results Comments
01/10/2023 COT - HCBU - Interior Shear Bracing N/A Partial Pass apartments 1-9 only
05/24/2023 COT - LCPL - Plumbing Final N/A Partial Pass hammer arrester required for dishwasher, fridge, and washer
05/24/2023 COT - LCBU - Building Final N/A Partial Pass
05/24/2023 COT - LCBU - CofO N/A Not Ready

Completed Inspections

Permit Status: Complete
Permit Number: T20CM03400
Permit Description: NEW MULTI FAMILY
Total Completed Inspections - 34
Date Description Inspector Results Comments
04/01/2022 COT - LCPL - Rough Soil Passed {Activity date: 04/01/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved for 13 units in building #3} ; {Activity date: 04/21/2021; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by VLEON1 - }
04/01/2022 COT - LCPL - Sewer Passed {Activity date: 04/01/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved for 13 units in building #3 connected to 8” private main}
04/22/2022 COT - LCEL - Electrical Underground Passed {Activity date: 04/22/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved}
04/22/2022 COT - LCBU - Excavation/Rebar/Zoning Passed {Activity date: 04/22/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved, PT Slab}
04/22/2022 COT - LCBU - Preslab Passed {Activity date: 04/22/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved all units building 3

}
04/22/2022 COT - LCEL - Grounding/Bonding Passed {Activity date: 04/22/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved all units building 3}
08/25/2022 COT - LCBU - Exterior Clips/Sheathing Passed {Activity date: 08/25/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. Ok to cover exterior walls.} ; {Activity date: 08/24/2022; Status: Cancelled; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - canceled per Tom. Contractor.}
08/25/2022 COT - LCBU - Roof Nailing Passed {Activity date: 08/25/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. Ok to dry in roof system.} ; {Activity date: 08/24/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - not ready. Need access to roof}
10/10/2022 COT - LCPL - Yard Water Line Passed {Activity date: 10/10/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - - Approved for building 3, okay to backfill progress areas}
12/06/2022 COT - LCEL - Electrical Intermediate Passed
12/06/2022 COT - LCPL - Plumbing Intermediate Passed
12/06/2022 COT - LCBU - Firewall/Fire Barrier/Firestop Passed
12/06/2022 COT - LCME - Mechanical Above Ceiling Passed
12/06/2022 COT - LCPL - Plumbing Above Ceiling Passed
12/06/2022 COT - LCBU - Building Above Ceiling Passed
12/06/2022 COT - LCME - Mechanical Intermediate Passed
01/18/2023 COT - HCBU - Interior Shear Bracing Passed
03/06/2023 COT - LCEL - Construction Power Passed Units 3101, 3102, 3103, 3104, 3105, 3106, 3107, 3108, 3109, 3110, 3111, 3112, and 3113.
03/03/2023 BULD - Electrical Clearance Passed ECO Clearance to TEP is required for the construction power (units #3101, 3102, 3103, 3104, 3105, 3106, 3107, 3108, 3109, 3110, 3111, 3112, and 3113)
05/24/2023 COT - LCBU - Building Progress Passed
05/24/2023 COT - LCEL - Electrical Progress Passed
05/24/2023 COT - HCBU - Exterior Clips/Sheathing Passed
05/24/2023 COT - LCPL - Plumbing Progress Passed
05/24/2023 COT - LCME - Mechanical Final Passed
05/24/2023 COT - LCME - Mechanical Progress Passed
05/24/2023 COT - LCEL - Electrical Final Passed
05/24/2023 COT - LCEL - Electrical Above Ceiling Passed
05/24/2023 COT - LCBU - Framing Passed
05/24/2023 COT - LCBU - Sustainability Passed
05/24/2023 COT - LCEL - Outdoor Lighting Passed
05/24/2023 COT - LCPL - Backwater Valve Passed
05/31/2023 COT - LCBU - Building Final Passed Temporary construction fence is up and secure preventing public access to Buildings 4, 5, & 6.
05/31/2023 COT - LCBU - CofO Passed Temporary construction fence is up and secure preventing public access to Buildings 4, 5, & 6. Okay to issue Level 4 Certificate of Occupancy.
06/07/2023 COT - FCON - Fire - Final Passed

Documents

File Name Document Type  
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
GEOTECH.PDF DOCUMENTS VIEW
SPECIAL INSPECTION CERT.PDF DOCUMENTS VIEW
PETITION OF APPEAL.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
STRUCTURAL CALCS.PDF DOCUMENTS VIEW
WAIVER AUTH.PDF DOCUMENTS VIEW