Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
06/02/2020
Applicant:
Gregory Moore
Description:
NEW MULTI FAMILY: 19-Unit Apartment Builiding

Permit Reviews

Permit Number - T20CM03330
Permit Status: Complete
Permit Description: NEW MULTI FAMILY: 19-Unit Apartment Builiding
Start Date Submittal Complete Date Status  
01/14/2021 RESUBMITTAL 01/20/2021 COMPLETED Review Details
06/04/2020 PLANS OK TO SUBMIT - COMM 07/24/2020 COMPLETED Review Details
07/24/2020 COMMERCIAL - NEW 09/14/2020 COMPLETED Review Details
08/02/2022 3RD PARTY REVIEW - COMMERCIAL 08/02/2022 ACTIVE Review Details
11/06/2020 RESUBMITTAL 12/08/2020 COMPLETED Review Details
11/06/2020 RESUBMITTAL 12/14/2020 COMPLETED Review Details

Conditions

Permit Number - T20CM03330
Permit Status: Complete
Permit Description: NEW MULTI FAMILY: 19-Unit Apartment Builiding
Date Description Comments
06/02/2020 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
06/08/2023 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: T20CM03330
Permite Description: NEW MULTI FAMILY: 19-Unit Apartment Builiding
Total Outstanding Inspections - 8
Last Inspection Date Description Inspector Results Comments
10/26/2022 COT - LCPL - Plumbing Final N/A Not Ready
10/26/2022 COT - LCME - Mechanical Intermediate N/A Not Ready
10/26/2022 COT - LCPL - Plumbing Above Ceiling N/A Not Ready
10/26/2022 COT - LCBU - Firewall/Fire Barrier/Firestop N/A Not Ready
04/18/2023 COT - LCBU - Building Final N/A Partial Pass awaiting grab bars in ada units and hammer arresters for dishwashers and refrigerators recommend level 3 TCO
09/15/2023 ENGR Engineering Final N/A Partial Pass This site has been Inspected to see what items will need to be addressed before the Development Package can be Approved and placed into Final Status. The Following items have been noted as needing to be addressed prior to this site being allowed to be Closed. A re-inspection of the site will be required once all comments have been addressed.

A) Complete the landscaping as shown on the approved plans and provide revised drawings for all changes that have been made to the site since the plans were original approved.

B) Complete the grading of all the landscape areas in, around, or adjacent to this site as shown on the approved plans, and ensure that all plant material has been installed accordingly.
10/26/2022 COT - FCON - Fire - Final N/A Not Ready
04/18/2023 COT - LCBU - CofO N/A Partial Pass recommend level 3 TCO

Completed Inspections

Permit Status: Complete
Permit Number: T20CM03330
Permit Description: NEW MULTI FAMILY: 19-Unit Apartment Builiding
Total Completed Inspections - 35
Date Description Inspector Results Comments
02/15/2022 COT - LCPL - Rough Soil Passed {Activity date: 02/15/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved for all of Building 1, this inspection was units 1101-1105} ; {Activity date: 01/25/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial approval for Building 1, units 1106- 1112} ; {Activity date: 01/24/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Not Ready} ; {Activity date: 01/04/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - - Partial approval for Building 1, units 1113 - 1119}
02/15/2022 COT - LCPL - Sewer Passed {Activity date: 02/15/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved for all of Building 1, this inspection was units 1101-1105 tied into private 4” line} ; {Activity date: 01/25/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial approval for Building 1, units 1106- 1112 tied into private 4” line

} ; {Activity date: 01/24/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Not Ready} ; {Activity date: 01/04/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial approval for Building 1, units 1113 - 1119 tied into private 4” line

}
02/15/2022 COT - LCPL - Backwater Valve Passed {Activity date: 02/15/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved, at unit 1101}
03/03/2022 COT - LCEL - Electrical Underground Passed {Activity date: 03/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved for Building 1 (units 1101-1105 today)} ; {Activity date: 02/14/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial for Building 1- units 1106 - 1112 (7 units)} ; {Activity date: 01/14/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - PARTIAL BUILDING 1- EAST 7 UNITS ok concrete placement.}
03/03/2022 COT - LCBU - Excavation/Rebar/Zoning Passed {Activity date: 03/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved for Building 1 (units 1101-1105 today)} ; {Activity date: 02/14/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial for Building 1- units 1106 - 1112 (7 units) ok to pour concrete in progress area} ; {Activity date: 01/14/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - PARTIAL BUILDING 1- EAST 7 UNITS ok concrete placement.}
03/03/2022 COT - LCBU - Preslab Passed {Activity date: 03/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved for Building 1 (units 1101-1105 today)} ; {Activity date: 02/14/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - - Partial for Building 1- units 1106 - 1112 (7 units)

}
03/03/2022 COT - LCEL - Grounding/Bonding Passed {Activity date: 03/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved for Building 1 (units 1101-1105 today)} ; {Activity date: 02/14/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial for Building 1- units 1106 - 1112 (7 units)} ; {Activity date: 01/14/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, uffer installed for future services for BUILDING 1- EAST 7 UNITS ok to proceed.}
06/16/2022 COT - LCBU - Roof Nailing Passed {Activity date: 06/16/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved with Fire treated plywood, okay to dry-in

}
06/23/2022 COT - LCBU - Exterior Clips/Sheathing Passed {Activity date: 06/23/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved}
09/20/2022 COT - LCPL - Yard Water Line Passed {Activity date: 09/20/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - Approved. Shading required.}
10/19/2022 COT - LCBU - Building Above Ceiling Passed {Activity date: 10/19/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 10/18/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - partial. 1101- 1106. Okay to proceed.
} ; {Activity date: 06/23/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Not Ready}
10/19/2022 COT - LCEL - Electrical Intermediate Passed {Activity date: 10/19/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 10/18/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - partial. 1101- 1106. Okay to proceed.
}
10/19/2022 COT - LCBU - Framing Passed {Activity date: 10/19/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 10/18/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - partial. 1101- 1106. Okay to proceed.
}
10/19/2022 COT - LCME - Mechanical Above Ceiling Passed {Activity date: 10/19/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 10/18/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - partial. 1101- 1106. Okay to proceed.
}
10/19/2022 COT - LCPL - Plumbing Intermediate Passed {Activity date: 10/19/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 10/18/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - partial. 1101- 1106. Okay to proceed.
}
10/19/2022 COT - LCBU - Sustainability Passed {Activity date: 10/19/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 10/18/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - partial. 1101- 1106. Okay to proceed.
}
10/19/2022 COT - LCEL - Electrical Above Ceiling Passed {Activity date: 10/19/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 10/18/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - partial. 1101- 1106. Okay to proceed.
}
11/09/2022 COT - HCBU - Interior Shear Bracing Passed
03/06/2023 COT - LCEL - Construction Power Passed 1101, 1102, 1103, 1104, 1105, 1106, 1107, 1108, 1109, 1110, 1111, 1112, 1113, 1114, 1115, 1116, 1117, 1118, and 1119.
04/18/2023 COT - LCPL - Plumbing Final Passed
04/18/2023 COT - LCME - Mechanical Intermediate Passed
04/18/2023 COT - LCPL - Plumbing Above Ceiling Passed
04/18/2023 COT - LCBU - Firewall/Fire Barrier/Firestop Passed
04/18/2023 COT - LCME - Mechanical Progress Passed
04/18/2023 COT - LCME - Mechanical Final Passed
04/18/2023 COT - HCBU - Exterior Clips/Sheathing Passed
04/18/2023 COT - LCBU - Building Progress Passed
04/18/2023 COT - LCEL - Electrical Final Passed
04/18/2023 COT - LCEL - Outdoor Lighting Passed
04/18/2023 COT - LCPL - Plumbing Progress Passed
04/18/2023 COT - LCEL - Electrical Progress Passed
09/15/2023 COT - LCBU - Building Final Passed 9/15/23: CofO
09/15/2023 COT - FCON - Fire - Final Passed
09/18/2023 COT - LCBU - CofO Passed 9/18/23: CofO
09/18/2023 BULD - Electrical Clearance Passed

Documents

File Name Document Type  
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
GEOTECH.PDF DOCUMENTS VIEW
SPECIAL INSPECTION CERT.PDF DOCUMENTS VIEW
PETITION OF APPEAL.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
WAIVER AUTH.PDF DOCUMENTS VIEW
STRUCTURAL CALCS.PDF DOCUMENTS VIEW
PLAN SET CONSTRPLANS VIEW