Permit: T20CM03330
Permit Details
Apply Date:
06/02/2020
Applicant:
Gregory Moore
Description:
NEW MULTI FAMILY: 19-Unit Apartment Builiding
Permit Reviews
Permit Number - T20CM03330
Permit Status: Complete
Permit Description: NEW MULTI FAMILY: 19-Unit Apartment Builiding
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/14/2021 | RESUBMITTAL | 01/20/2021 | COMPLETED |
06/04/2020 | PLANS OK TO SUBMIT - COMM | 07/24/2020 | COMPLETED |
07/24/2020 | COMMERCIAL - NEW | 09/14/2020 | COMPLETED |
08/02/2022 | 3RD PARTY REVIEW - COMMERCIAL | 08/02/2022 | ACTIVE |
11/06/2020 | RESUBMITTAL | 12/08/2020 | COMPLETED |
11/06/2020 | RESUBMITTAL | 12/14/2020 | COMPLETED |
Conditions
Permit Number - T20CM03330
Permit Status: Complete
Permit Description: NEW MULTI FAMILY: 19-Unit Apartment Builiding
Date | Description | Comments |
---|---|---|
06/02/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
06/08/2023 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T20CM03330
Permite Description: NEW MULTI FAMILY: 19-Unit Apartment Builiding
Total Outstanding Inspections - 8
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - LCPL - Plumbing Final | N/A | Not Ready | |
10/26/2022 | COT - LCME - Mechanical Intermediate | N/A | Not Ready | |
10/26/2022 | COT - LCPL - Plumbing Above Ceiling | N/A | Not Ready | |
10/26/2022 | COT - LCBU - Firewall/Fire Barrier/Firestop | N/A | Not Ready | |
04/18/2023 | COT - LCBU - Building Final | N/A | Partial Pass | awaiting grab bars in ada units and hammer arresters for dishwashers and refrigerators recommend level 3 TCO |
09/15/2023 | ENGR Engineering Final | N/A | Partial Pass | This site has been Inspected to see what items will need to be addressed before the Development Package can be Approved and placed into Final Status. The Following items have been noted as needing to be addressed prior to this site being allowed to be Closed. A re-inspection of the site will be required once all comments have been addressed. A) Complete the landscaping as shown on the approved plans and provide revised drawings for all changes that have been made to the site since the plans were original approved. B) Complete the grading of all the landscape areas in, around, or adjacent to this site as shown on the approved plans, and ensure that all plant material has been installed accordingly. |
10/26/2022 | COT - FCON - Fire - Final | N/A | Not Ready | |
04/18/2023 | COT - LCBU - CofO | N/A | Partial Pass | recommend level 3 TCO |
Completed Inspections
Permit Status: Complete
Permit Number: T20CM03330
Permit Description: NEW MULTI FAMILY: 19-Unit Apartment Builiding
Total Completed Inspections - 35
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/15/2022 | COT - LCPL - Rough Soil | Passed | {Activity date: 02/15/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved for all of Building 1, this inspection was units 1101-1105} ; {Activity date: 01/25/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial approval for Building 1, units 1106- 1112} ; {Activity date: 01/24/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Not Ready} ; {Activity date: 01/04/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - - Partial approval for Building 1, units 1113 - 1119} | |
02/15/2022 | COT - LCPL - Sewer | Passed | {Activity date: 02/15/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved for all of Building 1, this inspection was units 1101-1105 tied into private 4” line} ; {Activity date: 01/25/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial approval for Building 1, units 1106- 1112 tied into private 4” line } ; {Activity date: 01/24/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Not Ready} ; {Activity date: 01/04/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial approval for Building 1, units 1113 - 1119 tied into private 4” line } |
|
02/15/2022 | COT - LCPL - Backwater Valve | Passed | {Activity date: 02/15/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved, at unit 1101} | |
03/03/2022 | COT - LCEL - Electrical Underground | Passed | {Activity date: 03/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved for Building 1 (units 1101-1105 today)} ; {Activity date: 02/14/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial for Building 1- units 1106 - 1112 (7 units)} ; {Activity date: 01/14/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - PARTIAL BUILDING 1- EAST 7 UNITS ok concrete placement.} | |
03/03/2022 | COT - LCBU - Excavation/Rebar/Zoning | Passed | {Activity date: 03/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved for Building 1 (units 1101-1105 today)} ; {Activity date: 02/14/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial for Building 1- units 1106 - 1112 (7 units) ok to pour concrete in progress area} ; {Activity date: 01/14/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - PARTIAL BUILDING 1- EAST 7 UNITS ok concrete placement.} | |
03/03/2022 | COT - LCBU - Preslab | Passed | {Activity date: 03/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved for Building 1 (units 1101-1105 today)} ; {Activity date: 02/14/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - - Partial for Building 1- units 1106 - 1112 (7 units) } |
|
03/03/2022 | COT - LCEL - Grounding/Bonding | Passed | {Activity date: 03/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved for Building 1 (units 1101-1105 today)} ; {Activity date: 02/14/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial for Building 1- units 1106 - 1112 (7 units)} ; {Activity date: 01/14/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, uffer installed for future services for BUILDING 1- EAST 7 UNITS ok to proceed.} | |
06/16/2022 | COT - LCBU - Roof Nailing | Passed | {Activity date: 06/16/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved with Fire treated plywood, okay to dry-in } |
|
06/23/2022 | COT - LCBU - Exterior Clips/Sheathing | Passed | {Activity date: 06/23/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} | |
09/20/2022 | COT - LCPL - Yard Water Line | Passed | {Activity date: 09/20/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - Approved. Shading required.} | |
10/19/2022 | COT - LCBU - Building Above Ceiling | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 10/18/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - partial. 1101- 1106. Okay to proceed. } ; {Activity date: 06/23/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Not Ready} |
|
10/19/2022 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 10/18/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - partial. 1101- 1106. Okay to proceed. } |
|
10/19/2022 | COT - LCBU - Framing | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 10/18/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - partial. 1101- 1106. Okay to proceed. } |
|
10/19/2022 | COT - LCME - Mechanical Above Ceiling | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 10/18/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - partial. 1101- 1106. Okay to proceed. } |
|
10/19/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 10/18/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - partial. 1101- 1106. Okay to proceed. } |
|
10/19/2022 | COT - LCBU - Sustainability | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 10/18/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - partial. 1101- 1106. Okay to proceed. } |
|
10/19/2022 | COT - LCEL - Electrical Above Ceiling | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 10/18/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - partial. 1101- 1106. Okay to proceed. } |
|
11/09/2022 | COT - HCBU - Interior Shear Bracing | Passed | ||
03/06/2023 | COT - LCEL - Construction Power | Passed | 1101, 1102, 1103, 1104, 1105, 1106, 1107, 1108, 1109, 1110, 1111, 1112, 1113, 1114, 1115, 1116, 1117, 1118, and 1119. | |
04/18/2023 | COT - LCPL - Plumbing Final | Passed | ||
04/18/2023 | COT - LCME - Mechanical Intermediate | Passed | ||
04/18/2023 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
04/18/2023 | COT - LCBU - Firewall/Fire Barrier/Firestop | Passed | ||
04/18/2023 | COT - LCME - Mechanical Progress | Passed | ||
04/18/2023 | COT - LCME - Mechanical Final | Passed | ||
04/18/2023 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
04/18/2023 | COT - LCBU - Building Progress | Passed | ||
04/18/2023 | COT - LCEL - Electrical Final | Passed | ||
04/18/2023 | COT - LCEL - Outdoor Lighting | Passed | ||
04/18/2023 | COT - LCPL - Plumbing Progress | Passed | ||
04/18/2023 | COT - LCEL - Electrical Progress | Passed | ||
09/15/2023 | COT - LCBU - Building Final | Passed | 9/15/23: CofO | |
09/15/2023 | COT - FCON - Fire - Final | Passed | ||
09/18/2023 | COT - LCBU - CofO | Passed | 9/18/23: CofO | |
09/18/2023 | BULD - Electrical Clearance | Passed |