Permit: T20CM03299
Permit Details
Status:
Inspections Complete
Type:
Residential Building - One or Two Family
Address:
405 N GRANADA AV 09
Address NEW:
405 N GRANADA AV 09
Apply Date:
05/29/2020
Applicant:
Cindy Hogan
Description:
REMODEL AND ADD SECOND FLOOR SFR
Permit Reviews
Permit Number - T20CM03299
Permit Status: Inspections complete
Permit Description: REMODEL AND ADD SECOND FLOOR SFR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/29/2020 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 07/24/2020 | COMPLETED |
| 07/24/2020 | RESUBMITTAL | 08/17/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM03299
Permit Status: Inspections complete
Permit Description: REMODEL AND ADD SECOND FLOOR SFR
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/29/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: T20CM03299
Permite Description: REMODEL AND ADD SECOND FLOOR SFR
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/31/2023 | COT - RSPL - Plumbing Final | N/A | Re-inspection required | 10/31/23: water hammer arrestor missing at dishwasher, s-trap at upstairs bathroom. |
| 10/31/2023 | COT - RSPL - Rough Soil | N/A | Not Applicable | |
| 10/31/2023 | COT - RSPL - Yard Water Line | N/A | Not Applicable | |
| 10/31/2023 | RSBU - Building Final | N/A | Re-inspection required | 10/31/23: water hammer arrestor missing at dishwasher, s-trap at upstairs bathroom. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: T20CM03299
Permit Description: REMODEL AND ADD SECOND FLOOR SFR
Total Completed Inspections - 11
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/23/2020 | COT - RSBU - Roof Nailing | Passed | {Activity date: 12/23/2020; Status: Approved; Inspector: DQUINN; Comment: Entered by RSALDAT1 - Ap} | |
| 12/23/2020 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | {Activity date: 12/23/2020; Status: Approved; Inspector: DQUINN; Comment: Entered by RSALDAT1 - Ap} | |
| 02/18/2021 | COT - LCBU - Framing | Passed | {Activity date: 02/18/2021; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - Approved} | |
| 06/24/2021 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 06/24/2021; Status: Approved; Inspector: JBURGE; Comment: Entered by VLEON1 - Approved. Ok to insulate and cover walls. } |
|
| 06/24/2021 | RSME - Mechanical Progress | Passed | {Activity date: 06/24/2021; Status: Approved; Inspector: JBURGE; Comment: Entered by VLEON1 - Approved. Ok to insulate and cover walls. } |
|
| 02/23/2022 | COT - BULD - SWG Clearance | Passed | {Activity date: 02/23/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - CODE GAS} | |
| 02/23/2022 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 02/23/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. CLEARANCE: Ok to set gas meter. Called in to SW Gas at,1445 hours.} |
|
| 03/21/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 03/21/2023 | COT - RSME - Mechanical Final | Passed | ||
| 03/21/2023 | COT - RSEL - Electrical Final | Passed | ||
| 04/16/2024 | RSBU - Building Final | Passed |