Permit: T20CM03277
Permit Details
Status:
L of c
Type:
COMMERCIAL ALTERATION
Address:
2555 N JACKRABBIT AV
Address NEW:
2555 N JACKRABBIT AV
Apply Date:
05/29/2020
Applicant:
WATSON, JAMES RICHARD
Description:
TI: OFFICE/WAREHOUSE
Architects:
- WATSON, JAMES RICHARD
Permit Reviews
Permit Number - T20CM03277
Permit Status: L of c
Permit Description: TI: OFFICE/WAREHOUSE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/29/2020 | COMMERCIAL - TI | 06/04/2020 | COMPLETED |
| 06/04/2020 | RESUBMITTAL | 06/26/2020 | COMPLETED |
| 06/26/2020 | RESUBMITTAL | 06/30/2020 | COMPLETED |
| 09/22/2020 | REVISION - - 1ST | 11/05/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM03277
Permit Status: L of c
Permit Description: TI: OFFICE/WAREHOUSE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/29/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T20CM03277
Permit Description: TI: OFFICE/WAREHOUSE
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/13/2020 | PLUMBING - BACK WATER VALVE | ESTEVENS | Approved | Both are approved. |
| 07/13/2020 | PLUMBING - ROUGH, SOIL | ESTEVENS | Approved | Both are approved. |
| 07/16/2020 | BUILDING PRE-SLAB | ESTEVENS | Approved | Both are approved. |
| 07/16/2020 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVENS | Approved | Both are approved. |
| 10/05/2020 | ROOF NAILING | DMUNIZ | Approved | Approved, Warehouse addition second floor decking. |
| 02/18/2021 | PLUMBING - INTERMEDIATE | DQUINN | Approved | 00035 Ap Ok to rock |
| 02/18/2021 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | 00035 Ap Ok to rock |
| 02/18/2021 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | 00035 Ap Ok to rock |
| 02/18/2021 | FRAMING | DQUINN | Approved | 00035 Ap Ok to rock |
| 02/18/2021 | BUILDING ABOVE CEILING | DQUINN | Approved | 00036 Ap |
| 02/18/2021 | ELECTRIC - ABOVE CEILING | DQUINN | Approved | 00036 Ap |
| 08/16/2021 | ELECTRIC - FINAL | DQUINN | Approved | Ap |
| 08/16/2021 | MECHANICAL - FINAL | DQUINN | Approved | Ap |
| 08/16/2021 | ENGINEERING - FINAL | MHERNANDEZ | Approved | 9027 (ENGINEERING - FINAL) APPROVED /NO WORK WAS DONE OUTSIDE. |
| 08/17/2021 | FIRE - FINAL | CBASALDUA | Approved | |
| 08/17/2021 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
| 08/24/2021 | BUILDING - PROGRESS | DQUINN | Approved | Ap Close permit and issue C of O or L of C |
| 08/26/2021 | BUILDING - FINAL | DQUINN | Approved | Ap Close permit |
| 08/26/2021 | PLUMBING - FINAL | DQUINN | Approved | Ap Close permit |
| 08/26/2021 | BUILDING - FINAL | DQUINN | Approved | pa When all other entities are Ap, Ap 1090 |