Permit: T20CM03255
Permit Details
Apply Date:
05/28/2020
Applicant:
GEORGE HOLGUIN
Description:
CHANGE OF ISE OFFICE TO SALON
Architects:
- GEORGE HOLGUIN
Permit Reviews
Permit Number - T20CM03255
Permit Status: Final
Permit Description: CHANGE OF ISE OFFICE TO SALON
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/28/2020 | COMMERCIAL - TI | 06/02/2020 | COMPLETED |
06/02/2020 | RESUBMITTAL | 06/04/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM03255
Permit Status: Final
Permit Description: CHANGE OF ISE OFFICE TO SALON
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
05/28/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T20CM03255
Permit Description: CHANGE OF ISE OFFICE TO SALON
Total Completed Inspections - 19
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/09/2020 | ENGINEERING - FINAL | RLEDONNE | Approved | Approved. No work outside of building per approved plans. FaceTime inspection. Face Time inspection. |
06/11/2020 | PLUMBING - ABOVE CEILING | ESTEVENS | Approved | N/A |
06/11/2020 | SITE - SEWER | ESTEVENS | Approved | N/A |
06/11/2020 | ELECTRIC - FINAL | ESTEVENS | Approved | N/A |
06/11/2020 | ELECTRIC - ABOVE CEILING | ESTEVENS | Approved | N/A |
06/11/2020 | ELECTRIC - INTERMEDIATE | ESTEVENS | Approved | N/A |
06/11/2020 | PLUMBING - ROUGH, SOIL | ESTEVENS | Approved | |
06/30/2020 | BUILDING - FINAL | ESTEVENS | Approved | AIR BAL SUBMITTED, INSPECTOR APPROVED BUILDING FINAL. |
06/30/2020 | MECHANICAL - FINAL | ESTEVENS | Approved | AIR BAL RPT SUBMITTED SEE PREVIOUS ENTRY IN THIS TIEM NUMBER. INSPECTOR HAS APPROVED MECHANICAL FINAL. |
06/30/2020 | MECHANICAL - INTERMEDIATE | ESTEVENS | Approved | all six are approved. |
06/30/2020 | BUILDING - FINAL | RSHERRY | Approved | |
06/30/2020 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
06/30/2020 | BUILDING - FINAL | ESTEVENS | Approved | Partial. Pending air balance report. |
06/30/2020 | PLUMBING - FINAL | ESTEVENS | Approved | all six are approved. |
06/30/2020 | PLUMBING - INTERMEDIATE | ESTEVENS | Approved | all six are approved. |
06/30/2020 | BUILDING - PROGRESS | ESTEVENS | Approved | all six are approved. |
06/30/2020 | BUILDING ABOVE CEILING | ESTEVENS | Approved | all six are approved. |
06/30/2020 | FRAMING | ESTEVENS | Approved | all six are approved. |
07/06/2020 | CERTIFICATE OF OCCUPANCY | TTREMBULAK | Approved | Approved |