Permit: T20CM03064
Permit Details
Apply Date:
05/18/2020
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
MEDICAL OFFICE
Contractors:
- VENTURE WEST CONTRUCTION LLC
Permit Reviews
Permit Number - T20CM03064
Permit Status: C of o
Permit Description: MEDICAL OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/04/2021 | 3RD PARTY REVIEW - REVISION/OTHER | 04/07/2021 | COMPLETED |
05/18/2020 | COMMERCIAL - TI | 06/11/2020 | COMPLETED |
06/11/2020 | RESUBMITTAL - TI ALL | 07/20/2020 | COMPLETED |
09/24/2020 | REVISION - - 1ST | 10/20/2020 | COMPLETED |
10/20/2020 | REVISION - - 1ST | 11/05/2020 | COMPLETED |
11/05/2020 | REVISION - - 1ST | 11/23/2020 | COMPLETED |
12/01/2020 | REVISION - - 2ND | 12/02/2020 | COMPLETED |
12/02/2020 | 3RD PARTY REVIEW - REVISION/OTHER-2ND | 01/27/2021 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM03064
Permit Status: C of o
Permit Description: MEDICAL OFFICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
05/18/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T20CM03064
Permit Description: MEDICAL OFFICE
Total Completed Inspections - 30
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/16/2020 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVENS | Approved | Approved. |
10/28/2020 | ELECTRIC - UNDERGROUND | DQUINN | Approved | na |
10/28/2020 | REINFORCED MASONRY PRE-GROUT | DQUINN | Approved | pa N. W. Side stems on shell ok to pour. 2 ufer/bond connections in footings ok. |
11/06/2020 | PLUMBING - ROUGH, SOIL | DQINN | Approved | Ap This is for new TI, as well as main trunk into the adjacent shell. |
11/25/2020 | BUILDING PRE-SLAB | DQUINN | Approved | Ap |
02/22/2021 | FRAMING | DQUINN | Approved | APPROVED, OK TO 2 SIDE ALL WALLS |
02/22/2021 | PLUMBING - INTERMEDIATE | DQUINN | Approved | APPROVED |
02/22/2021 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | APPROVED |
02/25/2021 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | APPROVED ALL ABOVE CEILING OK TO HARD LID BATHROOMS |
03/05/2021 | SHEET ROCK NAILING | TGAUSP | Approved | |
04/07/2021 | PLUMBING - ROOF DRAINS | DQUINN | Approved | Note: main TI 4”pvc drain, outside of building, connection to existing building drain ok to backfill |
04/21/2021 | ELECTRIC - ABOVE CEILING | RELEFANTE | Approved | |
04/21/2021 | BUILDING ABOVE CEILING | RELEFANTE | Approved | |
05/18/2021 | BUILDING - PROGRESS | DQUINN | Approved | |
05/18/2021 | BUILDING - PROGRESS | DQUINN | Approved | APPROVED CONSULT FOR FINAL PREP |
05/19/2021 | RIGHT OF WAY - FINAL | D.Robertson | Approved | no ROW issues |
05/19/2021 | MECHANICAL - FINAL | RELEFANTE | Approved | |
05/19/2021 | PLUMBING - FINAL | RELEFANTE | Approved | |
05/19/2021 | ELECTRIC - FINAL | RELEFANTE | Approved | |
05/19/2021 | NPPO - FINAL | BBENEDON | Approved | |
05/19/2021 | SIGN - FINAL | BBENEDON | Approved | |
05/20/2021 | FIRE - FINAL | wmotto1 | Approved | |
05/20/2021 | FIRE - ALARM FINAL | wmotto1 | Approved | |
05/20/2021 | FIRE SPKLR - FINAL | wmotto1 | Approved | |
05/20/2021 | ROOF NAILING | RELEFANTE | Approved | |
05/20/2021 | EXT METAL CLIPS/EXT SHEATHING | RELEFANTE | Approved | |
05/21/2021 | ELECTRIC - SERVICE UPGRADE | DQUINN | Approved | |
05/21/2021 | LANDSCAPE - FINAL | DROBERTS | Approved | |
05/21/2021 | ENGINEERING - FINAL | DROBERTS | Approved | |
05/28/2021 | BUILDING - FINAL | DQUINN | Approved | APPROVED OK FOR C OF O |