Permit: T20CM02707
Permit Details
Apply Date:
04/30/2020
Applicant:
WILLIAMS, WILLIAM
Description:
ADDITION: RETAIL STORE
Permit Reviews
Permit Number - T20CM02707
Permit Status: C of o
Permit Description: ADDITION: RETAIL STORE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/30/2020 | PLANS OK TO SUBMIT - COMM | 06/02/2020 | COMPLETED |
06/02/2020 | COMMERCIAL - TI | 07/13/2020 | COMPLETED |
06/03/2020 | RESUBMITTAL - TI ALL | 07/21/2020 | COMPLETED |
07/21/2020 | RESUBMITTAL | 09/09/2020 | COMPLETED |
12/02/2020 | REVISION - - 1ST | 01/14/2021 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM02707
Permit Status: C of o
Permit Description: ADDITION: RETAIL STORE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
04/30/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T20CM02707
Permit Description: ADDITION: RETAIL STORE
Total Completed Inspections - 26
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/03/2020 | MECHANICAL - FINAL | RSHERRY | Approved | AIR BALANCE REPORT REQUIRED |
08/18/2020 | ELECTRIC - UNDERGROUND | TTREMBULAK | Approved | Approved, including UFER. |
08/18/2020 | EXCAVATION/LAYOUT REBAR & ZON | TTREMBULAK | Approved | Approved |
08/27/2020 | PLUMBING - ROUGH, SOIL | WGALLAGHER | Approved | Approved |
09/08/2020 | BUILDING - PROGRESS | TTREMBULAK | Approved | Partial. Pedestal and column bases... ok to pour concrete. |
09/16/2020 | BUILDING PRE-SLAB | TTREMBULAK | Approved | Approved |
10/30/2020 | EXT METAL CLIPS/EXT SHEATHING | WGALLAGHER | Approved | |
10/30/2020 | REINFORCED MASONRY PRE-GROUT | WGALLAGHER | Approved | Approved 16 posts |
10/30/2020 | EXT METAL CLIPS/EXT SHEATHING | WGALLAGHER | Approved | |
10/30/2020 | REINFORCED MASONRY PRE-GROUT | WGALLAGHER | Approved | Approved 16 posts |
11/04/2020 | FRAMING | DQUINN | Approved | Electric is all run in post chases. |
11/18/2020 | MECHANICAL - INTERMEDIATE | WGALLAGHER | Approved | |
11/18/2020 | ELECTRIC - INTERMEDIATE | WGALLAGHER | Approved | |
11/18/2020 | U VALUE FOR WINDOW | WGALLAGHER | Approved | |
12/16/2020 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |
01/07/2021 | OUTDOOR LIGHTING FINAL | RCHANDLER | Approved | AP |
01/07/2021 | ELECTRIC - ABOVE CEILING | RCHANDLER | Approved | AP |
01/07/2021 | ELECTRIC - OUTDOOR LIGHTING | RCHANDLER | Approved | AP |
01/07/2021 | ELECTRIC - FINAL | RCHANDLER | Approved | AP |
01/14/2021 | FIRE - FINAL | jfordney | Approved | |
01/14/2021 | FIRE - ALARM FINAL | jfordney | Approved | |
01/14/2021 | FIRE SPKLR - FINAL | jfordney | Approved | |
01/14/2021 | BUILDING ABOVE CEILING | WGALLAGHER | Approved | APPROVED |
02/05/2021 | ENGINEERING - FINAL | DROBERTS | Approved | APPROVED. THE ONLY ITEM FOR THE DEVELOPMENT PACKAGE IS LANDSCAPING CHANGES THAT NEED TO BE APPROVED |
02/26/2021 | CERTIFICATE OF OCCUPANCY | CTREVIL | Approved | |
02/26/2021 | BUILDING - FINAL | CTREVIL | Approved |