Permit: T20CM02682
Permit Details
Apply Date:
04/29/2020
Applicant:
DUSTIN GANGWER
Description:
ADDITION: 2 BEDROOMS, KITCHEN, ENTRY
Permit Reviews
Permit Number - T20CM02682
Permit Status: Final
Permit Description: ADDITION: 2 BEDROOMS, KITCHEN, ENTRY
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/29/2020 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 06/23/2020 | COMPLETED |
06/23/2020 | RESUBMITTAL | 09/02/2020 | COMPLETED |
09/03/2020 | RESUBMITTAL | 09/15/2020 | COMPLETED |
10/30/2020 | REVISION - - 1ST | 03/01/2021 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM02682
Permit Status: Final
Permit Description: ADDITION: 2 BEDROOMS, KITCHEN, ENTRY
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
04/29/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T20CM02682
Permit Description: ADDITION: 2 BEDROOMS, KITCHEN, ENTRY
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/24/2020 | TEP CLEARANCE - PM | JBURGE | Approved | CODE TMPP |
09/24/2020 | ELECTRIC - CONSTRUCTION POWER | JBURGE | Approved | Approved. Ok to energize for construction power. Clearance. Code: TMPP |
11/10/2020 | PLUMBING - ROUGH, SOIL | ESTEVENS | Approved | Approved. |
11/13/2020 | ELECTRIC - UFER | ESTEVENS | Approved | |
11/13/2020 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVENS | Approved | |
11/13/2020 | BUILDING PRE-SLAB | ESTEVENS | Approved | |
12/16/2020 | ROOF NAILING | ESTEVENS | Approved | APPROVED |
12/16/2020 | EXT METAL CLIPS/EXT SHEATHING | ESTEVENS | Approved | APPROVED |
01/13/2021 | GAS CLEARANCE | DQUINN | Approved | CODE |
01/13/2021 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | APPROVED |
01/13/2021 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | APPROVED |
01/13/2021 | RESIDENTIAL INTERMEDIATE | DQUINN | Approved | APPROVED |
01/13/2021 | FRAMING | DQUINN | Approved | APPROVED |
06/09/2021 | ELECTRIC - SERVICE RELOCATION | DQUINN | Approved | |
06/25/2021 | PLUMBING - INTERMEDIATE | RELEFANTE | Approved | |
06/25/2021 | MECHANICAL - INTERMEDIATE | RELEFANTE | Approved | |
06/25/2021 | MECHANICAL - FINAL | RELEFANTE | Approved | |
06/25/2021 | PLUMBING - FINAL | RELEFANTE | Approved | |
06/25/2021 | OUTDOOR LIGHTING FINAL | RELEFANTE | Approved | |
06/25/2021 | ELECTRIC - FINAL | RELEFANTE | Approved | |
06/25/2021 | BUILDING - FINAL | RELEFANTE | Approved |