Permit: T20CM02678
Permit Details
Apply Date:
04/29/2020
Applicant:
MIRAMONTE ARIZONA L L C *APA*
Description:
SFR MIRA154919 T19-M0019
Contractors:
- MIRAMONTE ARIZONA L L C *APA*
Permit Reviews
Permit Number - T20CM02678
Permit Status: Final
Permit Description: SFR MIRA154919 T19-M0019
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/29/2020 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 04/30/2020 | ACTIVE |
Completed Inspections
Permit Status: Final
Permit Number: T20CM02678
Permit Description: SFR MIRA154919 T19-M0019
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/21/2020 | PLUMBING - SEWER HCS CONNECT | ESTEVENS | Approved | |
05/21/2020 | PLUMBING - YARD WTR LINE/TEST | ESTEVENS | Approved | |
05/21/2020 | PLUMBING - ROUGH, SOIL | ESTEVENS | Approved | |
05/28/2020 | ELECTRIC - UNDERGROUND | ESTEVENS | Approved | |
05/28/2020 | BUILDING PRE-SLAB | ESTEVENS | Approved | |
05/28/2020 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVENS | Approved | |
06/26/2020 | ROOF NAILING | WGALLAGHER | Approved | Approved |
06/26/2020 | EXT METAL CLIPS/EXT SHEATHING | WGALLAGHER | Approved | Approved |
07/21/2020 | MECHANICAL - INTERMEDIATE | WGALLAGHER | Approved | Approved |
07/21/2020 | PLUMBING - GAS PRESSURE TEST | WGALLAGHER | Approved | Approved |
07/21/2020 | PLUMBING - INTERMEDIATE | WGALLAGHER | Approved | Approved |
07/21/2020 | RESIDENTIAL INTERMEDIATE | WGALLAGHER | Approved | Approved |
07/21/2020 | FRAMING | WGALLAGHER | Approved | Approved |
08/03/2020 | SHEET ROCK NAILING | WGALLAGHER | Approved | Approved |
08/24/2020 | TEP CLEARANCE - PM | TTREMBULAK | Approved | CODE ECO |
08/24/2020 | ELECTRIC - CONSTRUCTION POWER | TTREMBULAK | Approved | Approved Clearance for TEP ECO connect ok |
08/24/2020 | ELECTRIC - UFER | TTREMBULAK | Approved | Approved |
09/21/2020 | GAS CLEARANCE | DQUINN | Approved | CODE |
09/21/2020 | MECHANICAL - FINAL | DQUINN | Approved | Ap |
09/21/2020 | PLUMBING - FINAL | DQUINN | Approved | Ap |
09/21/2020 | ELECTRIC - FINAL | DQUINN | Approved | Ap |
09/29/2020 | BUILDING - FINAL | KEN | Approved | CERT FILED |