Permit: T20CM02456
Permit Details
Apply Date:
04/21/2020
Applicant:
GPD GROUP
Description:
RESTAURANT
Permit Reviews
Permit Number - T20CM02456
Permit Status: C of o
Permit Description: RESTAURANT
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/21/2020 | PLANS OK TO SUBMIT - COMM | 05/20/2020 | COMPLETED |
| 05/20/2020 | COMMERCIAL - TI | 05/28/2020 | COMPLETED |
| 06/26/2020 | RESUBMITTAL | 07/08/2020 | COMPLETED |
| 08/10/2020 | REVISION - - 1ST | 08/24/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM02456
Permit Status: C of o
Permit Description: RESTAURANT
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 04/21/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T20CM02456
Permit Description: RESTAURANT
Total Completed Inspections - 28
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/03/2020 | PLUMBING - PRE SLAB | ESTEVENS | Approved | Allseven are approved. |
| 09/03/2020 | ELECTRIC - INTERMEDIATE | ESTEVENS | Approved | Allseven are approved. |
| 09/03/2020 | PLUMBING - INTERMEDIATE | ESTEVENS | Approved | Allseven are approved. |
| 09/03/2020 | PLUMBING - ROUGH, SOIL | ESTEVENS | Approved | Allseven are approved. |
| 09/03/2020 | ELECTRIC - PROGRESS | ESTEVENS | Approved | Allseven are approved. |
| 09/03/2020 | BUILDING - PROGRESS | ESTEVENS | Approved | Allseven are approved. |
| 09/03/2020 | FRAMING | ESTEVENS | Approved | Allseven are approved. |
| 09/15/2020 | GAS CLEARANCE | ESTEVENS | Approved | CODE |
| 09/15/2020 | PLUMBING - GAS PRESSURE TEST | ESTEVENS | Approved | Approved. Southwest gas clearance is required. |
| 09/23/2020 | BUILDING ABOVE CEILING | DQUINN | Approved | Ap |
| 09/23/2020 | ELECTRIC - ABOVE CEILING | DQUINN | Approved | Ap |
| 09/23/2020 | PLUMBING - ABOVE CEILING | DQUINN | Approved | Ap |
| 09/23/2020 | PLUMBING - GAS PRESS TEST FNL | DQUINN | Approved | Ap Ok to drop lid |
| 09/23/2020 | MECHANICAL - ABOVE CEILING | DQUINN | Approved | Ap Ok to drop lid |
| 09/24/2020 | FIRE - FINAL | wmotto1 | Approved | |
| 09/24/2020 | FIRE - KITCHEN EXH HOOD FINAL | wmotto1 | Approved | |
| 09/24/2020 | SIGN - FINAL | BBENEDON | Approved | Approved. |
| 09/25/2020 | ENGINEERING - FINAL | BBENEDON | Approved | Approved. |
| 09/29/2020 | ELECTRIC - FINAL | ESTEVENS | Approved | Both are approved. |
| 09/29/2020 | PLUMBING - FINAL | ESTEVENS | Approved | Both are approved. |
| 09/30/2020 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
| 10/01/2020 | MECHANICAL - PROGRESS | DQUINN | Approved | 1090 |
| 10/01/2020 | MECHANICAL - HOODS | DQUINN | Approved | 1090 |
| 10/01/2020 | PLUMBING - PROGRESS | DQUINN | Approved | 1090 |
| 10/01/2020 | ROOF NAILING | DQUINN | Approved | 1090 |
| 10/01/2020 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | 1090 |
| 10/02/2020 | BUILDING - FINAL | CTREVIL | Approved | |
| 10/02/2020 | HEALTH DEPT - FINAL 724-7908 | P.URBINA | Approved |