Permit: T20CM02444
Permit Details
Apply Date:
04/20/2020
Applicant:
Andrea Flood
Description:
SFR F60B19 T19-M0028
Permit Reviews
Permit Number - T20CM02444
Permit Status: Expired
Permit Description: SFR F60B19 T19-M0028
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/23/2020 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 04/27/2020 | COMPLETED |
06/22/2020 | REVISION - - 1ST | 06/26/2020 | COMPLETED |
Conditions
Permit Number - T20CM02444
Permit Status: Expired
Permit Description: SFR F60B19 T19-M0028
Date | Description | Comments |
---|---|---|
04/20/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Expired
Permit Number: T20CM02444
Permite Description: SFR F60B19 T19-M0028
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/04/2022 | COT - FCON - Sprinkler - Final | N/A | Canceled | Inspection Canceled |
Completed Inspections
Permit Status: Expired
Permit Number: T20CM02444
Permit Description: SFR F60B19 T19-M0028
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/06/2020 | COT - RSPL - Yard Water Line | Passed | {Activity date: 08/06/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} | |
08/06/2020 | COT - RSPL - Sewer | Passed | {Activity date: 08/06/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} | |
08/06/2020 | COT - RSPL - Rough Soil | Passed | {Activity date: 08/06/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} | |
08/13/2020 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 08/13/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by JSCHNEI2 - Approved} | |
08/13/2020 | COT - RSEL - Electrical Underground | Passed | {Activity date: 08/13/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by JSCHNEI2 - Approved} | |
08/13/2020 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 08/13/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by JSCHNEI2 - Approved} | |
09/17/2020 | COT - RSBU - Roof Nailing | Passed | {Activity date: 09/17/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by JSCHNEI2 - Approved} | |
09/17/2020 | COT - LCBU - Framing | Passed | {Activity date: 09/17/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by JSCHNEI2 - Approved} | |
09/17/2020 | COT - RSBU - Preslab | Passed | {Activity date: 09/17/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by JSCHNEI2 - Approved} | |
09/17/2020 | COT - RSBU - Exterior Clips/Sheathing | Passed | {Activity date: 09/17/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by JSCHNEI2 - Approved} | |
10/30/2020 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 10/30/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by PAHUMAD1 - Approved screws in toilet flange} ; {Activity date: 10/28/2020; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by PAHUMAD1 - Inspection canceled by contractor} | |
10/30/2020 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 10/30/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by PAHUMAD1 - CODE ECO} | |
10/30/2020 | COT - RSEL - Construction Power | Passed | {Activity date: 10/30/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by PAHUMAD1 - CODE ECO} ; {Activity date: 10/30/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by PAHUMAD1 - Approved ok for clearance eco} ; {Activity date: 10/28/2020; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by PAHUMAD1 - Inspection canceled by contractor} | |
10/30/2020 | COT - BULD - SWG Clearance | Passed | {Activity date: 10/30/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by PAHUMAD1 - CODE} | |
10/30/2020 | RSME - Mechanical Progress | Passed | {Activity date: 10/30/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by PAHUMAD1 - } ; {Activity date: 10/28/2020; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by PAHUMAD1 - Inspection canceled by contractor} | |
10/30/2020 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 10/30/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by PAHUMAD1 - Approved ok for clearance} ; {Activity date: 10/28/2020; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by PAHUMAD1 - Inspection canceled by contractor} | |
12/03/2020 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 12/03/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by PAHUMAD1 - } ; {Activity date: 12/02/2020; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by PAHUMAD1 - Inspection canceled by contractor} | |
02/09/2021 | COT - RSME - Mechanical Final | Passed | {Activity date: 02/09/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - APPROVED} ; {Activity date: 01/20/2021; Status: Cancelled; Inspector: RCHANDLER; Comment: Entered by VLEON1 - CANCELLED} ; {Activity date: 01/15/2021; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - CANCELLED BY CONTRACTOR} | |
02/09/2021 | RSBU - Building Final | Passed | {Activity date: 02/09/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - APPROVED} ; {Activity date: 01/20/2021; Status: Cancelled; Inspector: RCHANDLER; Comment: Entered by VLEON1 - CANCELLED} ; {Activity date: 01/15/2021; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - CANCELLED BY CONTRACTOR} | |
02/09/2021 | COT - RSEL - Outdoor Lighting | Passed | {Activity date: 02/09/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - APPROVED} | |
02/09/2021 | COT - RSPL - Plumbing Final | Passed | {Activity date: 02/09/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - APPROVED} ; {Activity date: 01/20/2021; Status: Cancelled; Inspector: RCHANDLER; Comment: Entered by VLEON1 - CANCELLED} ; {Activity date: 01/15/2021; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - CANCELLED BY CONTRACTOR} | |
02/09/2021 | COT - RSEL - Electrical Final | Passed | {Activity date: 02/09/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - APPROVED} ; {Activity date: 01/20/2021; Status: Cancelled; Inspector: RCHANDLER; Comment: Entered by VLEON1 - CANCELLED} ; {Activity date: 01/15/2021; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - CANCELLED BY CONTRACTOR} |