Permit Details

Status:
Expired
Type:
Commercial Building
Address NEW:
2660 N ALVERNON WY
Apply Date:
04/20/2020
Applicant:
Valerie Saenz Pope
Description:
CHILLER & COOLING TOWER REPLACEMENT

Permit Reviews

Permit Number - T20CM02437
Permit Status: Expired
Permit Description: CHILLER & COOLING TOWER REPLACEMENT
Start Date Submittal Complete Date Status  
04/20/2020 COMMERCIAL - TI 07/31/2020 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T20CM02437
Permit Status: Expired
Permit Description: CHILLER & COOLING TOWER REPLACEMENT
Total Outstanding Activity Conditions - 5
Date Name
04/20/2020 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
05/06/2020 SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY.
05/06/2020 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
05/06/2020 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
05/06/2020 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.

Outstanding Inspections

Permit Status: Expired
Permit Number: T20CM02437
Permite Description: CHILLER & COOLING TOWER REPLACEMENT
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
11/07/2022 COT - LCBU - Building Final N/A Canceled Inspection Canceled

Completed Inspections

Permit Status: Expired
Permit Number: T20CM02437
Permit Description: CHILLER & COOLING TOWER REPLACEMENT
Total Completed Inspections - 10
Date Description Inspector Results Comments
09/04/2020 COT - LCEL - Electrical Intermediate Passed {Activity date: 09/04/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by JSCHNEI2 - Approved.}
09/04/2020 COT - LCBU - Framing Passed {Activity date: 09/04/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by JSCHNEI2 - All five are approved by Conformatech Engineering. See attached scanned documents.}
09/04/2020 COT - LCME - Mechanical Final Passed {Activity date: 09/04/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by JSCHNEI2 - Approved.}
09/04/2020 COT - LCBU - Excavation/Rebar/Zoning Passed {Activity date: 09/04/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by JSCHNEI2 - All five are approved by Conformatech Engineering. See attached scanned documents.}
09/04/2020 COT - LCBU - Preslab Passed {Activity date: 09/04/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by JSCHNEI2 - All five are approved by Conformatech Engineering. See attached scanned documents.}
09/04/2020 ENGR Engineering Final Passed {Activity date: 09/04/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - Approved.}
09/04/2020 COT - LCBU - Building Progress Passed {Activity date: 09/04/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by JSCHNEI2 - All five are approved by Conformatech Engineering. See attached scanned documents.}
09/04/2020 COT - LCBU - Masonry Pregrout Passed {Activity date: 09/04/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by JSCHNEI2 - All five are approved by Conformatech Engineering. See attached scanned documents.}
10/15/2020 COT - LCEL - Electrical Final Passed {Activity date: 10/15/2020; Status: Approved; Inspector: DQUINN; Comment: Entered by JSCHNEI2 - Ap} ; {Activity date: 09/04/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by JSCHNEI2 - Partial. Label M1. panel and chiller disconnects remove all abandon wires}
10/20/2020 COT - LCPL - Gas Pressure Test Passed {Activity date: 10/20/2020; Status: Approved; Inspector: BSTEVENS; Comment: Entered by BSTEVENS - }