Permit: T20CM02437
Permit Details
Apply Date:
04/20/2020
Applicant:
Valerie Saenz Pope
Description:
CHILLER & COOLING TOWER REPLACEMENT
Permit Reviews
Permit Number - T20CM02437
Permit Status: Expired
Permit Description: CHILLER & COOLING TOWER REPLACEMENT
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/20/2020 | COMMERCIAL - TI | 07/31/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM02437
Permit Status: Expired
Permit Description: CHILLER & COOLING TOWER REPLACEMENT
Total Outstanding Activity Conditions - 5
Date | Name |
---|---|
04/20/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
05/06/2020 | SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY. |
05/06/2020 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
05/06/2020 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
05/06/2020 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
Outstanding Inspections
Permit Status: Expired
Permit Number: T20CM02437
Permite Description: CHILLER & COOLING TOWER REPLACEMENT
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/07/2022 | COT - LCBU - Building Final | N/A | Canceled | Inspection Canceled |
Completed Inspections
Permit Status: Expired
Permit Number: T20CM02437
Permit Description: CHILLER & COOLING TOWER REPLACEMENT
Total Completed Inspections - 10
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/04/2020 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 09/04/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by JSCHNEI2 - Approved.} | |
09/04/2020 | COT - LCBU - Framing | Passed | {Activity date: 09/04/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by JSCHNEI2 - All five are approved by Conformatech Engineering. See attached scanned documents.} | |
09/04/2020 | COT - LCME - Mechanical Final | Passed | {Activity date: 09/04/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by JSCHNEI2 - Approved.} | |
09/04/2020 | COT - LCBU - Excavation/Rebar/Zoning | Passed | {Activity date: 09/04/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by JSCHNEI2 - All five are approved by Conformatech Engineering. See attached scanned documents.} | |
09/04/2020 | COT - LCBU - Preslab | Passed | {Activity date: 09/04/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by JSCHNEI2 - All five are approved by Conformatech Engineering. See attached scanned documents.} | |
09/04/2020 | ENGR Engineering Final | Passed | {Activity date: 09/04/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - Approved.} | |
09/04/2020 | COT - LCBU - Building Progress | Passed | {Activity date: 09/04/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by JSCHNEI2 - All five are approved by Conformatech Engineering. See attached scanned documents.} | |
09/04/2020 | COT - LCBU - Masonry Pregrout | Passed | {Activity date: 09/04/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by JSCHNEI2 - All five are approved by Conformatech Engineering. See attached scanned documents.} | |
10/15/2020 | COT - LCEL - Electrical Final | Passed | {Activity date: 10/15/2020; Status: Approved; Inspector: DQUINN; Comment: Entered by JSCHNEI2 - Ap} ; {Activity date: 09/04/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by JSCHNEI2 - Partial. Label M1. panel and chiller disconnects remove all abandon wires} | |
10/20/2020 | COT - LCPL - Gas Pressure Test | Passed | {Activity date: 10/20/2020; Status: Approved; Inspector: BSTEVENS; Comment: Entered by BSTEVENS - } |