Permit: T20CM02281
Permit Details
Apply Date:
04/15/2020
Applicant:
BENJAMIN DESIGN
Description:
NEW SFR
Completed Inspections
Permit Status: Final
Permit Number: T20CM02281
Permit Description: NEW SFR
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/23/2021 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | APPROVED |
| 03/08/2021 | ELECTRIC - UFER | DQUINN | Approved | APPROVED |
| 03/08/2021 | BUILDING PRE-SLAB | DQUINN | Approved | APPROVED |
| 03/08/2021 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | APPROVED |
| 05/11/2021 | PLUMBING - SEWER HCS CONNECT | DQUINN | Approved | |
| 07/09/2021 | REINFORCED MASONRY PRE-GROUT | DQUINN | Approved | APPROVED OK TO GROUT SOUTH WALL TOP OUT |
| 09/03/2021 | TEP CLEARANCE - PM | RELEFANTE | Approved | CODE ECO |
| 09/03/2021 | ELECTRIC - CONSTRUCTION POWER | RELEFANTE | Approved | AP Clear ECO |
| 09/03/2021 | ROOF NAILING | RELEFANTE | Approved | DE( contractor covered roof with tyveck so I could not do the inspection and he didn’t want to take it off for me) |
| 10/07/2021 | FRAMING | JBURGE | Approved | Approved Ok to insulate and cover walls and ceilings. |
| 10/07/2021 | RESIDENTIAL INTERMEDIATE | JBURGE | Approved | . Approved |
| 10/07/2021 | PLUMBING - INTERMEDIATE | JBURGE | Approved | . Approved |
| 10/07/2021 | PLUMBING - YARD WTR LINE/TEST | JBURGE | Approved | . Approved |
| 10/07/2021 | PLUMBING - GAS PRESSURE TEST | JBURGE | Approved | . Approved |
| 10/07/2021 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | . Approved |
| 03/10/2022 | BUILDING - FINAL | DQUINN | Approved | APPROVED BY INSPECTOR AWAITING CONDITIONS |
| 03/10/2022 | GAS CLEARANCE | DQUINN | Approved | CODE |
| 03/10/2022 | BUILDING - FINAL | DQUINN | Approved | Ap |
| 03/10/2022 | ELECTRIC - UNDERGROUND | DQUINN | Approved | Ap |
| 03/10/2022 | ELECTRIC - FINAL | DQUINN | Approved | Ap |
| 03/10/2022 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | Ap Clear gas Close permit |
| 03/10/2022 | PLUMBING - FINAL | DQUINN | Approved | Ap |
| 03/10/2022 | MECHANICAL - FINAL | DQUINN | Approved | Ap |